Market Notices

119867MINIMUM SYSTEM LOAD04/11/2024 03:37:17 PM

Forecast Minimum System Load (MSL1) condition in the VIC region on 10/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 10/11/2024.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 - 1735 MW
- MSL2 - 1235 MW
- MSL3 - 735 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:
1. From 0930 hrs to 1230 hrs 10/11/2024. Minimum regional demand is forecast to be 1262 MW at 1230 hrs.
2. From 1300 hrs to 1500 hrs 10/11/2024. Minimum regional demand is forecast to be 1249 MW at 1330 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .

AEMO is seeking a market response.

AEMO Operations
     
119866MINIMUM SYSTEM LOAD04/11/2024 03:38:29 PM

Forecast Minimum System Load (MSL1) condition in the VIC region on 09/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 09/11/2024.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 - 1745 MW
- MSL2 - 1245 MW
- MSL3 - 745 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:
1. From 1100 hrs to 1400 hrs 09/11/2024. Minimum regional demand is forecast to be 1488 MW at 1300 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .

AEMO is seeking a market response.

AEMO Operations
     
119863MARKET INTERVENTION04/11/2024 02:37:24 PM

Forecast Minimum System Load MSL1 condition in the VIC Region on 05/11/2024

AEMO ELECTRICITY MARKET NOTICE
Forecast Minimum System Load MSL1 condition in the VIC Region on 05/11/2024

Update to Market Notice 119743 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 05/11/2024.

Minimum regional demand is forecast to be 1258 MW at 1300 hrs, and the advisory threshold is:
MSL1 - 1320 MW
MSL2 - 820 MW
MSL3 - 320 MW

The regional demand is forecast to be below the MSL1 threshold for the following period[s]:
From 1200 hrs 05/11/2024 to 1330 hrs 05/11/2024.

Manager NEM Real Time Operations
     
119859MARKET INTERVENTION04/11/2024 01:49:57 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0700 hrs 05/11/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
119852MINIMUM SYSTEM LOAD04/11/2024 08:53:24 AM

Forecast Minimum System Load MSL2 condition in the VIC region on 10/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 10/11/2024.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 = 1760 MW
- MSL2 = 1260 MW
- MSL3 = 760 MW

The regional demand is forecast to be below the MSL2 threshold for the following period:

From 1230 hrs 10/11/2024 to 1330 hrs 10/11/2024. Minimum regional demand is forecast to be 1236 MW at 1300 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb.

AEMO is seeking a market response.


AEMO Operations
     
119848MARKET INTERVENTION04/11/2024 07:58:26 AM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.


Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 119835

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1700 hrs 04/11/2024.

The direction update is issued at 0755 hrs 04/11/2024.

Manager NEM Real Time Operations
     
119847MARKET INTERVENTION04/11/2024 07:57:19 AM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 119836

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1630 hrs 04/11/2024.

The direction update is issued at 0755 hrs 04/11/2024.

Manager NEM Real Time Operations
     
119845MARKET SYSTEMS04/11/2024 07:46:34 AM

CHG0099569 | Production | Maintenance on Gas B2B Hub databases

Change Number: CHG0099569
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal

Service/ Component: Gas Hub
Change Title: Maintenance on Gas B2B Hub databases
Change Start Date & Time: 17/11/2024 10:00:00 AEST
Change End Date & Time: 17/11/2024 10:30:00 AEST

Outage Start Date & Time:
Outage End Date & Time:
Environment: Production

Participant Impact and Requirements: The following impacts are expected during this maintenance:
- Brief 5 to 10 seconds loss of connectivity to the Gas B2B Hub and all ebXML gateways (AEMOMIBB, AGNLGWY, LVI & VENCORP) during the outage window.
- Users are not required to take any action due to this change.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.

Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .

     
119836MARKET INTERVENTION03/11/2024 09:13:13 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 119831

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1700 hrs 04/11/2024.

The direction update is issued at 2115 hrs 03/11/2024.

Manager NEM Real Time Operations
     