Filter by category
Filter by Date
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 119747 has been updated at 1400 hrs 02/11/2024 to the following:
1. From 1330 hrs to 1530 hrs 07/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 834 MW.
2. From 1900 hrs to 2000 hrs 07/11/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 730 MW.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 119703 has been updated at 1400 hrs 01/11/2024 to the following:
1. From 1430 hrs to 1800 hrs 07/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 778 MW.
2. From 1900 hrs to 2000 hrs 07/11/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 832 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 04/11/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119572 has been updated at 1400 hrs 01/11/2024 to the following:
1. From 1730 hrs to 1930 hrs 04/11/2024.
The forecast capacity reserve requirement is 1120 MW.
The minimum capacity reserve available is 852 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 07/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:
1. From 1730 hrs to 1800 hrs 07/11/2024.
The forecast capacity reserve requirement is 978 MW.
The minimum capacity reserve available is 629 MW.
2. From 1900 hrs to 1930 hrs 07/11/2024.
The forecast capacity reserve requirement is 978 MW.
The minimum capacity reserve available is 754 MW.
AEMO Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region [beginning] on 31/10/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119693 is cancelled at 1720 hrs 31/10/2024.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1630 hrs to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1014 MW.
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 31/10/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119692 has been updated at 0945 hrs to the following:
[1.] From 1730 hrs 31/10/2024 to 2000 hrs 31/10/2024.
The forecast capacity reserve requirement is 1292 MW.
The minimum capacity reserve available is 925 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 31/10/2024
[1.] From 1830 hrs 31/10/2024 to 1900 hrs 31/10/2024.
The forecast capacity reserve requirement is 1285 MW.
The minimum capacity reserve available is 1248 MW.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Wagga B 330 kV Bus - NSW region - 31/10/2024
Inter-regional transfer limit variation - Wagga B 330 kV bus- NSW region - 31/10/2024
At 0028 hrs 31/10/2024 there was an unplanned outage of Wagga B 330 kV bus.
The following constraint set(s) invoked at 0045 hrs 31/10/2024
N-WAGGA_330_BUSB, N-JNWG_RADIAL, V-DBUSS_L and V-DBUSS_T
This constraint set(s) contains equations with the following interconnectors on the LHS.
VIC1-NSW1,N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations