Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 120013
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1730 hrs 07/11/2024.
The direction update is issued at 1208 hrs 07/11/2024.
Manager NEM Real Time Operations
[EventId:202411071155_review] Prices for interval 07-Nov-2024 11:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1150 hrs on 7 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 07-Nov-2024 11:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411071150_review] Prices for interval 07-Nov-2024 11:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1145 hrs on 7 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 07-Nov-2024 11:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411071145_review] Prices for interval 07-Nov-2024 11:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1140 hrs on 7 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 07-Nov-2024 11:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411071140_review] Prices for interval 07-Nov-2024 11:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1135 hrs on 7 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 07-Nov-2024 11:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411071135_review] Prices for interval 07-Nov-2024 11:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1130 hrs on 7 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 07-Nov-2024 11:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411071130_review] Prices for interval 07-Nov-2024 11:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1125 hrs on 7 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 07-Nov-2024 11:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Cancellation of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: NSW1
Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV
Cancellation time: 07/11/2024 07:19
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 120054
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: NSW1
Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV
Duration: 07/11/2024 05:14 until further notice
Constraint set(s) invoked:
NONE