Filter by category
Filter by Date
[EventId:202410291710_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 29 October 2024 17:10
Issued by Australian Energy Market Operator Ltd at 1710 hrs on 29 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1710 hrs on 29 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202410291500_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 29 October 2024 15:00
Issued by Australian Energy Market Operator Ltd at 1500 hrs on 29 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 October 2024.
Refer to market notice: 119642
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1500 hrs on 29 October 2024.
This is an AEMO autogenerated Market Notice.
Forecast Minimum System Load 1 (MSL1) in the VIC Region on 02/11/2024
Update to Market Notice 119571 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region on 02/11/2024.
Minimum regional demand is forecast to be 1457 MW at 1230 hrs, and the advisory threshold is:
MSL1 - 1695 MW
MSL2 - 1195 MW
MSL3 - 695 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1130 hrs to 1400 hrs 02/11/2024.
AEMO Operations
[EventId:202410291405_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 29 October 2024 14:05
Issued by Australian Energy Market Operator Ltd at 1405 hrs on 29 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1405 hrs on 29 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202410291230_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 29 October 2024 12:30
Issued by Australian Energy Market Operator Ltd at 1230 hrs on 29 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 October 2024.
Refer to market notice: 119627
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1230 hrs on 29 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410291140_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 29 October 2024 11:40
Issued by Australian Energy Market Operator Ltd at 1140 hrs on 29 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1140 hrs on 29 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202410291000_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 29 October 2024 10:00
Issued by Australian Energy Market Operator Ltd at 1000 hrs on 29 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 October 2024.
Refer to market notice: 119609
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1000 hrs on 29 October 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202410290905_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 29 October 2024 09:05
Issued by Australian Energy Market Operator Ltd at 0905 hrs on 29 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0905 hrs on 29 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202410290625_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 29 October 2024 06:25
Issued by Australian Energy Market Operator Ltd at 0625 hrs on 29 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 29 October 2024.
Refer to market notice: 119605
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.
The negative residue constraint NRM_QLD1_NSW1 ceased operating at 0625 hrs on 29 October 2024.
This is an AEMO autogenerated Market Notice.