Market Notices

120020PRICES SUBJECT TO REVIEW06/11/2024 05:05:21 PM

[EventId:202411061710_review] Prices for interval 06-Nov-2024 17:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1705 hrs on 6 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Nov-2024 17:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120019MARKET INTERVENTION06/11/2024 05:07:43 PM

Direction - SA region to AGL SA Generation Pty Limited - BARKER INLET PS

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - BARKER INLET PS

Refer to Market Notice 119875


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - BARKER INLET PS at 1655 hrs 06/11/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 1700 hrs 06/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1800 hrs 06/11/2024 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
120018PRICES SUBJECT TO REVIEW06/11/2024 05:01:16 PM

[EventId:202411061705_review] Prices for interval 06-Nov-2024 17:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1700 hrs on 6 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Nov-2024 17:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120017RECLASSIFY CONTINGENCY06/11/2024 04:59:13 PM

Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Cancellation time: 06/11/2024 16:59

Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Refer AEMO Electricity Market Notice 119997

Auto-generated on behalf of Manager NEM Real Time Operations
     
120015RECLASSIFY CONTINGENCY06/11/2024 04:30:18 PM

Cancellation of the reclassification of a Non-Credible contingency event: Rowville - Yallourn No. 7 220 kV Line and the Rowville - Yallourn No. 8 220 kV Line in VIC due to Lightning.

AEMO ELECTRICITY MARKET NOTICE.

Cancellation of the reclassification of a Non-Credible contingency event as a Credible contingency event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any Lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC

Lines: Rowville - Yallourn No. 7 220 kV Line and the Rowville - Yallourn No. 8 220 kV Line

Cancellation time: 16:30 hrs 06/11/2024

Constraint set(s) revoked:
V-ROYP78_R_N-2

Refer AEMO Electricity Market Notice 119964

Manager NEM Real Time Operations
     
120014MARKET INTERVENTION06/11/2024 04:04:29 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 120012

In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1600 hrs 06/11/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0800 hrs 07/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 08/11/2024 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
120013MARKET INTERVENTION06/11/2024 04:01:53 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 120012


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1600 hrs 06/11/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0730 hrs 07/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 08/11/2024 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
120012MARKET INTERVENTION06/11/2024 04:03:15 PM

Direction - SA region 06/11/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 06/11/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 06/11/2024.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations
     
120005PRICES SUBJECT TO REVIEW06/11/2024 03:25:16 PM

[EventId:202411061530_review] Prices for interval 06-Nov-2024 15:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1525 hrs on 6 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Nov-2024 15:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm