Market Notices

119948PRICES SUBJECT TO REVIEW06/11/2024 08:50:22 AM

[EventId:202411060855_review] Prices for interval 06-Nov-2024 08:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0850 hrs on 6 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Nov-2024 08:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
119947PRICES SUBJECT TO REVIEW06/11/2024 08:46:46 AM

[EventId:202411060850_review] Prices for interval 06-Nov-2024 08:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0845 hrs on 6 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Nov-2024 08:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
119945PRICES SUBJECT TO REVIEW06/11/2024 08:40:20 AM

[EventId:202411060845_review] Prices for interval 06-Nov-2024 08:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0840 hrs on 6 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Nov-2024 08:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
119944PRICES SUBJECT TO REVIEW06/11/2024 08:35:17 AM

[EventId:202411060840_review] Prices for interval 06-Nov-2024 08:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0835 hrs on 6 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 06-Nov-2024 08:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
119893INTER-REGIONAL TRANSFER05/11/2024 08:48:29 AM

Inter-regional transfer limit variation - Tamworth No 3 330 kV bus and Tamworth - Uralla No. 85 330 kV Line - NSW region - 05/11/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Tamworth No 3 330 kV bus and Tamworth - Uralla No. 85 330 kV Line - NSW region - 05/11/2024

A planned outage of Tamworth No 3 330 kV bus and Tamworth - Uralla No. 85 330 kV Line in the NSW region was scheduled to be completed at 1700 hrs 05/11/2024

The outage has been completed by 0840 hrs 05/11/2024.

Constraint set(s) invoked:
N-MUTW_88
N-TWUL_85
N-TW_SVC
N-DM_SVC
N-X_TW_330_BUS3-5

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1
T-V-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
119826INTER-REGIONAL TRANSFER03/11/2024 01:10:08 PM

Inter-regional transfer limit variation - three poles of Directlink - NSW region - 03/11/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - three poles of Directlink - NSW region - 03/11/2024

At 1330 hrs 03/11/2024 there will be a short notice outage of all three poles of Directlink.

The following constraint set(s) to be invoked at 1330 hrs 03/11/2024
N-X_MBTE_3

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
119804PRICES SUBJECT TO REVIEW02/11/2024 02:56:09 PM

[EventId:202411021500_review] Prices for interval 02-Nov-2024 15:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1455 hrs on 2 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 02-Nov-2024 15:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
119802PRICES SUBJECT TO REVIEW02/11/2024 02:50:38 PM

[EventId:202411021455_review] Prices for interval 02-Nov-2024 14:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1450 hrs on 2 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 02-Nov-2024 14:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
119801PRICES SUBJECT TO REVIEW02/11/2024 02:45:21 PM

[EventId:202411021450_review] Prices for interval 02-Nov-2024 14:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1445 hrs on 2 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 02-Nov-2024 14:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm