Inter-regional transfer limit variation - DAPTO - MARULAN 8 330KV LINE - NSW region - 07/05/2024
Inter-regional transfer limit variation - DAPTO - MARULAN 8 330KV LINE - NSW region - 07/05/2024
A planned outage of DAPTO - MARULAN 8 330KV LINE in the NSW region was scheduled from 0830 hrs 27/04/2024 to 1000 hrs 07/05/2024.
The outage has been rescheduled to be completed by 1200 hrs 08/05/2024.
Constraint set(s) invoked: N-DTMN_8_15M
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
[EventId:202405020855_review] Prices for interval 02-May-2024 08:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 0850 hrs on 2 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 02-May-2024 08:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405020850_review] Prices for interval 02-May-2024 08:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 0845 hrs on 2 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 02-May-2024 08:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405020845_review] Prices for interval 02-May-2024 08:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 0840 hrs on 2 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 02-May-2024 08:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405020840_review] Prices for interval 02-May-2024 08:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 0835 hrs on 2 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 02-May-2024 08:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405020835_review] Prices for interval 02-May-2024 08:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 0830 hrs on 2 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 02-May-2024 08:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405020830_review] Prices for interval 02-May-2024 08:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 0825 hrs on 2 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 02-May-2024 08:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405011735_review] Prices for interval 01-May-2024 17:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 1 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 01-May-2024 17:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405011730_review] Prices for interval 01-May-2024 17:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1725 hrs on 1 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 01-May-2024 17:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.