Non-credible contingency event - QLD region - 23/01/2024
Non-credible contingency event - QLD region - 23/01/2024
At 0957 hrs the Strathmore No 2 275 kV bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
The following constraint set(s) invoked
Q-NESTM
Q-X_NQ_275_FDR+BUS
Manager NEM Real Time Operations
[EventId:202401222005_review] Prices for interval 22-Jan-2024 20:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 2000 hrs on 22 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Jan-2024 20:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202401222000_review] Prices for interval 22-Jan-2024 20:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1955 hrs on 22 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Jan-2024 20:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202401221955_review] Prices for interval 22-Jan-2024 19:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1950 hrs on 22 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Jan-2024 19:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202401221950_review] Prices for interval 22-Jan-2024 19:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1945 hrs on 22 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Jan-2024 19:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202401221945_review] Prices for interval 22-Jan-2024 19:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1940 hrs on 22 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Jan-2024 19:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202401221940_review] Prices for interval 22-Jan-2024 19:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1935 hrs on 22 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 22-Jan-2024 19:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
PDPASA - Cancellation of the Actual Lack Of Reserve Level 1 (LOR1) in the QLD Region on 22/01/2024
The Actual LOR 1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113635 is cancelled at 1930 hrs 22/01/2024
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 22/01/2024
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 22/01/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1830 hrs.
The Actual LOR1 condition is forecast in Predispatch
The capacity reserve requirement is 986 MW
The minimum capacity reserve available is 969 MW
Manager NEM Real Time Operations