Inter-regional transfer limit variation - Blyth West to Munno Para 275 kV line - SA region - 08/05/2024
Inter-regional transfer limit variation - Blyth West to Munno Para 275 kV line - SA region - 08/05/2024
At 1536 hrs 08/05/2024 there was an unplanned outage of Blyth West to Munno Para 275 kV line.
The following constraint set(s) invoked at 1545 hrs 08/05/2024
S-X_BGBW+BWMP
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
[EventId:202405081300_review] Prices for interval 08-May-2024 13:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1255 hrs on 8 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-May-2024 13:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405081255_review] Prices for interval 08-May-2024 12:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1250 hrs on 8 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-May-2024 12:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405081250_review] Prices for interval 08-May-2024 12:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1245 hrs on 8 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-May-2024 12:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405081245_review] Prices for interval 08-May-2024 12:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1240 hrs on 8 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-May-2024 12:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405081240_review] Prices for interval 08-May-2024 12:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1235 hrs on 8 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-May-2024 12:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405081235_review] Prices for interval 08-May-2024 12:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1230 hrs on 8 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-May-2024 12:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Inter-regional transfer limit variation - Tamworth No. 1 330 kV Bus - NSW region - 08/05/2024
Inter-regional transfer limit variation - Tamworth No. 1 330 kV Bus - NSW region - 08/05/2024
A planned outage of Tamworth No. 1 330 kV Bus in the NSW region was scheduled from 1200 hrs 08/05/2024 to 1800 hrs 10/05/2024.
The outage has been cancelled at 1154 hrs 08/05/2024
Constraint set(s) revoked: N-TW_330_BUS1, N-LDTW_84
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1
N-Q-MNSP1
T-V-MNSP1
Manager NEM Real Time Operations
Inter-regional transfer limit variation - DAPTO - MARULAN 8 330KV LINE - NSW region - 07/05/2024
Inter-regional transfer limit variation - DAPTO - MARULAN 8 330KV LINE - NSW region - 07/05/2024
A planned outage of DAPTO - MARULAN 8 330KV LINE in the NSW region was scheduled from 0830 hrs 27/04/2024 to 1000 hrs 07/05/2024.
The outage has been rescheduled to be completed by 1200 hrs 08/05/2024.
Constraint set(s) invoked: N-DTMN_8_15M
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations