[EventId:202402131740_review] Prices for interval 13-Feb-2024 17:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 13 February 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Feb-2024 17:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202402131735_review] Prices for interval 13-Feb-2024 17:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 13 February 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Feb-2024 17:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202402131730_review] Prices for interval 13-Feb-2024 17:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1725 hrs on 13 February 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Feb-2024 17:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202402131725_review] Prices for interval 13-Feb-2024 17:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1720 hrs on 13 February 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Feb-2024 17:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202402131720_review] Prices for interval 13-Feb-2024 17:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1715 hrs on 13 February 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Feb-2024 17:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Significant power system event - Victoria Region - Hazelwood transformers -13/02/2024
At 1543 hrs 13/02/2024 At Hazelwood terminal station in the Victoria region the following plant tripped.
The No1 500 kV / 220 kV transformer
The No2 500 kV / 220 kV transformer
The No3 500 kV / 220 kV transformer
The No4 500 kV / 220 kV transformer
The Jeeralang Hazelwood No2 220kV line.
Refer Market notice 114641
Updates will be provided as additional information becomes available.
This Market Notice is issued in accordance with NER clause 4.8.3.
Manager NEM Real Time Operations
Non-credible contingency event - TAS region - 13/02/2024
Non-credible contingency event - TAS region - 13/02/2024
At 1602 hrs the Norwood -Scottsdale 110kV line and the Norwood - Scottsdale -Derby 110kV line tripped.
AEMO did not instruct load shedding.
AEMO has been advised 8MW of electrical load and 24MW of generation has been disconnected.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
[EventId:202402131520_review] Prices for interval 13-Feb-2024 15:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1515 hrs on 13 February 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Feb-2024 15:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202402131515_review] Prices for interval 13-Feb-2024 15:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1510 hrs on 13 February 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 13-Feb-2024 15:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs