114777MARKET INTERVENTION15/02/2024 08:50:44 PM

Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA region

The synchronous generating units currently expected to be synchronised in SA from 0830 hrs 16/02/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 2200 hrs 15/02/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
114774MARKET INTERVENTION15/02/2024 11:01:17 PM

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 14/02/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 14/02/2024

Refer Market Notice 114721

The AEMO Intervention Event and all associated directions are cancelled from 2300 hrs 15/02/2024

Manager NEM Real Time Operations
114770INTER-REGIONAL TRANSFER15/02/2024 07:34:10 PM

Inter-regional transfer limit variation - Moorabool Sydenham 500 kV lines - Vic region - 15/02/2024

AEMO ELECTRICITY MARKET NOTICE

At 1905 hrs 15/02/2024 in the Victoria region interim work was completed at Moorabool and Sydenham terminal stations to provide additional 500 kV bus ties.

As a result of this completed work the South Australia region is no longer on a credible risk of separation.

Constraint set changes.

Invoked:
V-X_MLSY_MLTS_TIE

Revoked:

F-V-X_ML_BUSTIE_500
I-VS_050
S-X_BC_CP
V-X_MLSY

This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1
V-SA
V-S-MNSP1
VIC1- NSW1
Rfer Market Notices 114577, 114768, 114686

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
114768MARKET INTERVENTION15/02/2024 07:05:26 PM

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction VIC region 14/02/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction VIC region 14/02/2024

Refer Market Notice 114697

The AEMO Intervention Event and all associated directions are cancelled from 1905 hrs 15/02/2024

Manager NEM Real Time Operations
114764MARKET INTERVENTION15/02/2024 03:55:07 PM

Update - Direction - SA Region - 14/02/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 14/02/2024

Refer Market Notice 114721

The AEMO intervention event that commenced from interval ending 1535 hrs on 14/02/2024 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
114761MARKET INTERVENTION15/02/2024 02:15:15 PM

Cancellation of Distributed PV Contingency 3 (DPVC3), Distributed PV Contingency 2 (DPVC2) and Distributed PV Contingency 1 (DPVC1) condition in the SA Region on 15/02/2024.

AEMO ELECTRICITY MARKET NOTICE

Cancellation - DPVC3, DPVC2 and DPVC1 - SA Region

Refer Market Notice 114751 for DPVC3, 114753 for DPVC2 and 114746 for DPVC1.

The DPVC3, DPVC2 and DPVC1 condition for 15/02/2024 is cancelled at 1415 hrs 15/02/2024.

Manager NEM Real Time Operations
114757MARKET INTERVENTION15/02/2024 01:28:07 PM

Update - Distributed PV Contingency 3 (DPVC3) in the SA Region on 15/02/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Distributed PV Contingency 3 (DPVC3) in the SA Region on 15/02/2024

Refer AEMO Electricity Participant Notice 114751

Distributed PV curtailment is occurring in the SA region to maintain system security due to a Distributed PV Contingency condition.

The instruction direction under National Electricity Law s116 to maintain demand above the required threshold is now expected to end at 1430 hrs 15/02/2024.


Manager NEM Real Time Operations
114753MARKET INTERVENTION15/02/2024 12:32:48 PM

Distributed PV Contingency 2 (DPVC2) in the SA Region on 15/02/2024

AEMO ELECTRICITY MARKET NOTICE
AEMO has taken action(s) to maintain power system security in South Australia at 1215 hrs 15/02/2024 due to a forecast Distributed PV Contingency (DPVC) condition.

AEMO actions may include the recall of planned outages, a direction and/or instruction to scheduled and non-scheduled generation, and/or an instruction direction to maintain DPV generation below a secure DPV generation threshold.

Manager NEM Real Time Operations
114751MARKET INTERVENTION15/02/2024 12:34:45 PM

Distributed PV Contingency 3 (DPVC3) in the SA Region on 15/02/2024

AEMO ELECTRICITY MARKET NOTICE

Distributed PV curtailment is occurring in the SA region to maintain system security due to a Distributed PV Contingency condition.

The instruction direction under National Electricity Law s.116 to maintain demand above the required threshold is expected to end at 1330 hrs 15/02/2024.


Manager NEM Real Time Operations