NON-CONFORMANCE Region NSW1 Tuesday, 21 May 2024
NON-CONFORMANCE NSW1 Region Tuesday, 21 May 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BW04
Duration: 21/05/2024 10:45 to 21/05/2024 10:50
Amount: -22 MW
Constraint: NC-N_BW04
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202405191545_review] Prices for interval 19-May-2024 15:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1540 hrs on 19 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 19-May-2024 15:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405191540_review] Prices for interval 19-May-2024 15:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1535 hrs on 19 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 19-May-2024 15:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405191535_review] Prices for interval 19-May-2024 15:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 19 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 19-May-2024 15:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405191530_review] Prices for interval 19-May-2024 15:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1525 hrs on 19 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 19-May-2024 15:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405191525_review] Prices for interval 19-May-2024 15:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1520 hrs on 19 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 19-May-2024 15:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405191520_review] Prices for interval 19-May-2024 15:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1515 hrs on 19 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 19-May-2024 15:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region QLD1 Sunday, 19 May 2024
NON-CONFORMANCE QLD1 Region Sunday, 19 May 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: PUMP2
Duration: 19/05/2024 07:35 to 19/05/2024 07:40
Amount: 240 MW
Constraint: NC-Q_PUMP2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Saturday, 18 May 2024
NON-CONFORMANCE QLD1 Region Saturday, 18 May 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 18/05/2024 02:40 to 18/05/2024 02:45
Amount: -14 MW
Constraint: NC-Q_MPP_1