PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 18/01/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113359 has been updated at 1550 hrs to the following:
[1.] From 1830 hrs 18/01/2024 to 1900 hrs 18/01/2024.
The forecast capacity reserve requirement is 1144 MW.
The minimum capacity reserve available is 1057 MW.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 22/01/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113280 is cancelled at 1400 hrs 17/01/2024.
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 19/01/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113279 is cancelled at 1400 hrs 17/01/2024.
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 18/01/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1730 hrs 18/01/2024 to 2000 hrs 18/01/2024.
The forecast capacity reserve requirement is 1247 MW.
The minimum capacity reserve available is 968 MW.
Manager NEM Real Time Operations
STPASA - Update to the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 19/01/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113279 has been updated at 1400 hrs 16/01/2024 to the following:
From 1830 hrs to 1900 hrs 19/01/2024.
The forecast capacity reserve requirement is 1180 MW.
The minimum capacity reserve available is 1040 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 22/01/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1830 hrs to 1900 hrs 22/01/2024.
The forecast capacity reserve requirement is 1242 MW.
The minimum capacity reserve available is 1109 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 19/01/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1830 hrs to 1900 hrs 19/01/2024.
The forecast capacity reserve requirement is 1253 MW.
The minimum capacity reserve available is 1161 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 18/01/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1730 hrs to 2030 hrs 18/01/2024.
The forecast capacity reserve requirement is 1247 MW.
The minimum capacity reserve available is 985 MW.
AEMO Operations
[EventId:202401111300_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 11 January 2024 13:00
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 11 January 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 11 January 2024.
Refer to market notice: 113205
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1300 hrs on 11 January 2024.