Filter by category
Filter by Date
[EventId:202402211825_NRM_SA1_VIC1_started] NEGRES CONSTRAINT NRM_SA1_VIC1 started operating from 21 February 2024 18:25
Issued by Australian Energy Market Operator Ltd at 1825 hrs on 21 February 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 21 February 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the SA to VIC directional interconnector.
The negative residue constraint set NRM_SA1_VIC1 commenced operating from 1825 hrs on 21 February 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 23/02/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1730 hrs to 1900 hrs 23/02/2024.
The forecast capacity reserve requirement is 1251 MW.
The minimum capacity reserve available is 1076 MW.
AEMO Operations
[EventId:202402211130_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 21 February 2024 11:30
Issued by Australian Energy Market Operator Ltd at 1130 hrs on 21 February 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 21 February 2024.
Refer to market notice: 114914
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1130 hrs on 21 February 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202402210955_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 21 February 2024 09:55
Issued by Australian Energy Market Operator Ltd at 0955 hrs on 21 February 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 21 February 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 0955 hrs on 21 February 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202402191515_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 19 February 2024 15:15
Issued by Australian Energy Market Operator Ltd at 1515 hrs on 19 February 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 19 February 2024.
Refer to market notice: 114879
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1515 hrs on 19 February 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202402191405_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 19 February 2024 14:05
Issued by Australian Energy Market Operator Ltd at 1405 hrs on 19 February 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 19 February 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1405 hrs on 19 February 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202402191200_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 19 February 2024 12:00
Issued by Australian Energy Market Operator Ltd at 1200 hrs on 19 February 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 19 February 2024.
Refer to market notice: 114873
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1200 hrs on 19 February 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202402191035_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 19 February 2024 10:35
Issued by Australian Energy Market Operator Ltd at 1035 hrs on 19 February 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 19 February 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1035 hrs on 19 February 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 23/02/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 114838 is cancelled at 1430 hrs 18/02/2024.
No LOR condition is currently forecast in the STPASA period.
Manager NEM RTO