PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 06/02/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 114357 has been updated at 1110 hrs to the following:
[1.] From 1730 hrs 06/02/2024 to 2030 hrs 06/02/2024.
The forecast capacity reserve requirement is 1014 MW.
The minimum capacity reserve available is 884 MW.
Manager NEM Real Time Operations
Fast Frequency Response Market - Increase in L1 FCAS dispatch cap from 12 February 2024.
Following review of the operation of the Very Fast FCAS market, from 1300 hrs AEST on Monday 12 Febraury AEMO will:
Increase the cap on dispatch of Very Fast Lower (L1) Contingency FCAS from 100 MW to 125 MW
Retain the cap on dispatch of Very Fast Raise (R1) Contingency FCAS at 225 MW
No other changes to the dispatch of Very Fast FCAS or FCAS constraint equation changes will be made on this date.
For information on the Fast Frequency Response (FFR) initiative please visit the website at: https://www.aemo.com.au/initiatives/major-programs/fast-frequency-response
Andrew Groom
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 06/02/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 114355 has been updated at 1000 hrs to the following:
[1.] From 1800 hrs 06/02/2024 to 1930 hrs 06/02/2024.
The forecast capacity reserve requirement is 1040 MW.
The minimum capacity reserve available is 1015 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 06/02/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1830 hrs 06/02/2024 to 1900 hrs 06/02/2024.
The forecast capacity reserve requirement is 1178 MW.
The minimum capacity reserve available is 1073 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 06/02/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 114347 is cancelled at 0510 hrs 06/02/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 06/02/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1830 hrs 06/02/2024 to 1900 hrs 06/02/2024.
The forecast capacity reserve requirement is 1125 MW.
The minimum capacity reserve available is 1073 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 06/02/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 114304 is cancelled at 1515hrs 05/02/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 06/02/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No.114296 has been updated at 1445hrs to the following:
[1.] From 1830 hrs 06/02/2024 to 1900 hrs 06/02/2024.
The forecast capacity reserve requirement is 1230 MW.
The minimum capacity reserve available is 1197 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 114298 is cancelled at 1445 hrs 05/02/2024.
Manager NEM Real Time Operations