Inter-regional transfer limit variation - Tamworth No 3 330 kV bus and Tamworth - Uralla No. 85 330 kV Line - NSW region - 05/11/2024
Inter-regional transfer limit variation - Tamworth No 3 330 kV bus and Tamworth - Uralla No. 85 330 kV Line - NSW region - 05/11/2024
A planned outage of Tamworth No 3 330 kV bus and Tamworth - Uralla No. 85 330 kV Line in the NSW region was scheduled to be completed at 1700 hrs 05/11/2024
The outage has been completed by 0840 hrs 05/11/2024.
Constraint set(s) invoked:
N-MUTW_88
N-TWUL_85
N-TW_SVC
N-DM_SVC
N-X_TW_330_BUS3-5
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1
T-V-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
NEM Local Temperature Alerts for QLD from 04 Nov 2024 to 08 Nov 2024
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
QLD
Dalby Ap (37+ Deg C): 5th Nov, 7th Nov, 8th Nov
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Inter-regional transfer limit variation - three poles of Directlink - NSW region - 03/11/2024
Inter-regional transfer limit variation - three poles of Directlink - NSW region - 03/11/2024
At 1330 hrs 03/11/2024 there will be a short notice outage of all three poles of Directlink.
The following constraint set(s) to be invoked at 1330 hrs 03/11/2024
N-X_MBTE_3
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
[EventId:202411021500_review] Prices for interval 02-Nov-2024 15:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1455 hrs on 2 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 02-Nov-2024 15:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411021455_review] Prices for interval 02-Nov-2024 14:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1450 hrs on 2 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 02-Nov-2024 14:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411021450_review] Prices for interval 02-Nov-2024 14:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1445 hrs on 2 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 02-Nov-2024 14:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411021445_review] Prices for interval 02-Nov-2024 14:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1440 hrs on 2 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 02-Nov-2024 14:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411021440_review] Prices for interval 02-Nov-2024 14:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1435 hrs on 2 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 02-Nov-2024 14:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411021435_review] Prices for interval 02-Nov-2024 14:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1430 hrs on 2 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 02-Nov-2024 14:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.