117027GENERAL NOTICE17/06/2024 10:59:14 AM

QNI Minor testing (Qld to NSW) 17th June 2024

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 114742

There is an opportunity for testing QNI Minor for flows from Qld to NSW up to 1300 MW on Monday 17th June 2024 from 1200 to 1800hrs.

This test includes a trip and reclose of a line in northern NSW.

Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade

Ben Blake
AEMO Operations
116899GENERAL NOTICE05/06/2024 12:11:55 PM

Network Augmentation Commissioned - QLD Region - 05/06/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - QLD Region - 05/06/2024

H20 Broadsound 275 kV Bus Reactor 1 (150 MVAr) has been commissioned as at 1043 hrs.

Manager NEM Real Time Operations
116879GENERAL NOTICE03/06/2024 10:49:16 AM

Fast Frequency Response Market - Increase in R1 and L1 FCAS dispatch caps from 11th June 2024

AEMO ELECTRICITY MARKET NOTICE

Following review of the operation of the Very Fast FCAS market, from 1300 hrs AEST on Tuesday 11th June AEMO will:

Increase the cap on dispatch of Very Fast Raise (R1) Contingency FCAS from 325 MW to 350 MW

Increase the cap on dispatch of Very Fast Lower (L1) Contingency FCAS from 200 MW to 225 MW

No other changes to the dispatch of Very Fast FCAS or FCAS constraint equation changes will be made on this date.

For information on the Fast Frequency Response (FFR) initiative please visit the website at: https://www.aemo.com.au/initiatives/major-programs/fast-frequency-response

Andrew Groom
AEMO Operations
116874GENERAL NOTICE01/06/2024 08:31:10 PM

Network Augmentation Commissioned - QLD Region - 01/06/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - QLD Region - 01/06/2024

H90 Tully South 275 kV Switching Station has been cut into the existing Ross - Woree No.8905 275 kV line to form the following circuits:

H13 Ross - H90 Tully South No.8905/1 275 kV line
H90 Tully South - H39 Woree No.8905/2 275 kV line

Manager NEM Real Time Operations
116630GENERAL NOTICE15/05/2024 06:00:51 PM

Update - Network Augmentation Commissioned - QLD Region - 15/05/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Network Augmentation Commissioned - QLD Region - 15/04/2024

Refer Market notice: 115974 and 116446

Guybal Munjan 275 kV Switching Station has been commissioned.

The former Ross - Chalumbin No. 857 and Ross - Chalumbin No. 858 275 kV lines have been replaced with the following lines:

H13 Ross - H93 Guybal Munjan No. 8916 275 kV line
H13 Ross - H93 Guybal Munjan No. 8917 275 kV line

H93 Guybal Munjan - H32 Chalumbin No. 857 275 kV line
H93 Guybal Munjan - H32 Chalumbin No. 858 275 kV line


Manager NEM Real Time Operations
116446GENERAL NOTICE02/05/2024 07:49:28 PM

Network Augmentation Commissioned - QLD Region - 02/05/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - QLD Region - 02/05/2024

Commissioned:

H13 Ross - H93 Guybal Munjan No.8917 275 kV line

Manager NEM Real Time Operations
116339POWER SYSTEM EVENTS26/04/2024 12:12:59 PM

Non-credible contingency event - NSW region - 26/04/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 26/04/2024

At 1112 hrs the Griffith to Darlington Point 132kV line (99K) and the Darlington Point BESS disconnected.

AEMO did not instruct load shedding.

AEMO observed 5 MW of electrical load lost.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
116329GENERAL NOTICE25/04/2024 11:56:40 AM

Planned outage of Gordon - Chapel St No. 1 220 kV line in the TAS region on 26/04/2024

AEMO ELECTRICITY MARKET NOTICE

The Gordon - Chapel St No. 1 220 kV line in the Tasmania (TAS) region is planned to be out of service from 1030 hrs on 26/04/2024 to 1500 hrs on 26/04/2024

A credible contingency event during this planned outage could cause a large reduction in generation in TAS.

Refer AEMO Network Outage Schedule (NOS) for further details.

Manager NEM Real Time Operations
116299POWER SYSTEM EVENTS24/04/2024 10:54:59 AM

Non-credible contingency event - QLD region - 24/04/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 24/04/2024

At 0855 hrs the Ross - Guybal Munjan 8916 275 kV line tripped at the Guybal Munjan end only.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.


Manager NEM Real Time Operations