Correction to testing time for Project Energy Connect (PEC-1) 6th November 2024 for flows in both directions
Refer to market notice 119961
This is correction to Project Energy Connect (PEC-1) testing time issued in previous notice 119961.
Testing time is on 6th November from 11:00 hrs to 22:00 hrs.
The test is for flows in both directions up to 50 MW. This test includes a trip and reclose of a line in South Australia. Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.
Mya San
AEMO Operations
Revised testing time for Project Energy Connect (PEC-1) 6th November 2024 for flows in both directions
Refer to market notice 119901
The Project Energy Connect (PEC-1) testing opportunity has changed ans it is now on 6th November at 22:00 hrs.
The test is for flows in both directions up to 50 MW.
This test includes a trip and reclose of a line in South Australia.
Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.
Terry Liu
AEMO Operations
[EventId:202411060910_review] Prices for interval 06-Nov-2024 09:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 0905 hrs on 6 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Nov-2024 09:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411060905_review] Prices for interval 06-Nov-2024 09:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 0900 hrs on 6 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Nov-2024 09:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411060900_review] Prices for interval 06-Nov-2024 09:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 0855 hrs on 6 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Nov-2024 09:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411060855_review] Prices for interval 06-Nov-2024 08:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 0850 hrs on 6 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Nov-2024 08:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411060850_review] Prices for interval 06-Nov-2024 08:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 0845 hrs on 6 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Nov-2024 08:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411060845_review] Prices for interval 06-Nov-2024 08:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 0840 hrs on 6 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Nov-2024 08:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411060840_review] Prices for interval 06-Nov-2024 08:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 0835 hrs on 6 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Nov-2024 08:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.