[EventId:202401212120_review] Prices for interval 21-Jan-2024 21:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 2115 hrs on 21 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 21-Jan-2024 21:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202401212115_review] Prices for interval 21-Jan-2024 21:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 2110 hrs on 21 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 21-Jan-2024 21:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 21/01/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 21/01/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 2000 hrs
The capacity reserve requirement is 1340 MW
The minimum capacity reserve available is 1103 MW
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the QLD region - 21/01/2024
Cancellation of Actual (LOR1) condition in the QLD region - 21/01/2024
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.113570 is cancelled at 2015 hrs 21/01/2024.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 21/01/2024
Cancellation of Actual (LOR1) condition in the NSW region - 21/01/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.113576 is cancelled at 1945 hrs 21/01/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 21/01/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 21/01/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is not forecast in Pre Dispatch
The capacity reserve requirement is 1360 MW
The minimum capacity reserve available is 1354 MW
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 21/01/2024
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 21/01/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 1238 MW
The minimum capacity reserve available is 988 MW
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the QLD region - 19/01/2024
Cancellation of Actual (LOR1) condition in the QLD region - 19/01/2024
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.113498 is cancelled at 2000 hrs 19/01/2024.
Manager NEM Real Time Operations
[EventId:202401191830_review] Prices for interval 19-Jan-2024 18:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1825 hrs on 19 January 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 19-Jan-2024 18:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs