Market Notices

113369MARKET INTERVENTION17/01/2024 04:15:29 PM

Update - Direction - SA Region - 16/01/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 16/01/2024

Refer Market Notice 113322

The AEMO intervention event that commenced from interval ending 1435 hrs on 16/01/2024 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
113357NON-CONFORMANCE17/01/2024 12:15:14 PM

NON-CONFORMANCE Region NSW1 Wednesday, 17 January 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 17 January 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BW04
Duration: 17/01/2024 12:00 to 17/01/2024 12:15
Amount: 21 MW
Constraint: NC-N_BW04

Auto-generated on behalf of Manager NEM Real Time Operations
113354NON-CONFORMANCE17/01/2024 10:20:15 AM

NON-CONFORMANCE Region QLD1 Wednesday, 17 January 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 17 January 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 17/01/2024 10:05 to 17/01/2024 10:20
Amount: 46 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
113352RESERVE NOTICE17/01/2024 10:00:51 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 19/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113346 is cancelled at 0900 hrs 17/01/2024.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
113351NON-CONFORMANCE17/01/2024 09:10:55 AM

NON-CONFORMANCE Region QLD1 Wednesday, 17 January 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 17 January 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 17/01/2024 09:05 to 17/01/2024 09:10
Amount: -149 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
113346RESERVE NOTICE17/01/2024 06:30:49 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 19/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

[1.] From 1530 hrs 19/01/2024 to 1600 hrs 19/01/2024.
The forecast capacity reserve requirement is 696 MW.
The minimum capacity reserve available is 677 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
113341RESERVE NOTICE17/01/2024 04:35:14 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 19/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice 113337 is cancelled at 0430 hrs 17/01/2024.

No LOR2 condition is currently forecast in the STPASA period.

Manager NEM Real Time Operations
113337RESERVE NOTICE17/01/2024 01:39:36 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 19/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

[1.] From 1500 hrs 19/01/2024 to 1600 hrs 19/01/2024.
The forecast capacity reserve requirement is 708 MW.
The minimum capacity reserve available is 671 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
113322MARKET INTERVENTION16/01/2024 02:30:55 PM

Direction - SA region 16/01/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 16/01/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1435 hrs on 16/01/2024.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations