Reclassification of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: VIC1
Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV
Duration: 11/09/2024 17:28 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202409111325_review] Prices for interval 11-Sep-2024 13:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1320 hrs on 11 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409111320_review] Prices for interval 11-Sep-2024 13:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1315 hrs on 11 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409111315_review] Prices for interval 11-Sep-2024 13:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1310 hrs on 11 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409111310_review] Prices for interval 11-Sep-2024 13:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1305 hrs on 11 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409111305_review] Prices for interval 11-Sep-2024 13:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 11 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409111300_review] Prices for interval 11-Sep-2024 13:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1255 hrs on 11 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 11-Sep-2024 13:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/09/2024
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 118202 is cancelled at 1100 hrs 09/09/2024.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 10/09/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
From 1830 hrs to 1930 hrs 10/09/2024.
The forecast capacity reserve requirement is 347 MW.
The minimum capacity reserve available is 343 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations