Market Notices

119202INTER-REGIONAL TRANSFER23/10/2024 06:42:52 AM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in VIC region - 23/10/2024

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the VIC region, AEMO has invoked automated constraint set CA_SYDS_562A9792 from 0635 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

V-S-MNSP1
V-SA
VIC1-NSW1

Refer to AEMO Network Outage Scheduler (NOS) for further information.

Manager NEM Real Time Operations
     
119056INTER-REGIONAL TRANSFER19/10/2024 01:10:23 PM

Inter-regional transfer limit variation - Tamworth No 1 330 kV bus and Tamworth - Armidale No. 86 330 kV Line - NSW region - 19/10/2024

AEMO ELECTRICITY MARKET NOTICE

Tamworth No 1 330 kV bus and Tamworth - Armidale No. 86 330 kV Line - NSW region - 19/10/2024

A planned outage of Tamworth No 1 330 kV bus in the NSW region was scheduled from 1100 hrs 18/10/2024 to 1700 hrs 20/10/2024.
A planned outage of Tamworth - Armidale No. 86 330 kV Line in the NSW region was scheduled from 0500 hrs 09/10/2024 to 1700 hrs 20/10/2024.

The outage has been completed by 1250 hrs 19/10/2024.

Constraint set(s) invoked:
N-ARTW_86
N-LDTW_84
N-TW_SVC
N-TW_330_BUS1

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1
T-V-MNSP1


Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
119046RECLASSIFY CONTINGENCY19/10/2024 02:54:16 AM

Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Cancellation time: 19/10/2024 02:54

Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Refer AEMO Electricity Market Notice 119045

Auto-generated on behalf of Manager NEM Real Time Operations
     
119045RECLASSIFY CONTINGENCY19/10/2024 01:51:36 AM

Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Duration: 19/10/2024 01:51 until further notice

Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Auto-generated on behalf of Manager NEM Real Time Operations
     
119044RECLASSIFY CONTINGENCY18/10/2024 11:54:16 PM

Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Cancellation time: 18/10/2024 23:54

Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Refer AEMO Electricity Market Notice 119041

Auto-generated on behalf of Manager NEM Real Time Operations
     
119042RECLASSIFY CONTINGENCY18/10/2024 09:34:25 PM

Cancellation of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV

Cancellation time: 18/10/2024 21:34

Constraint set(s) revoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1


Refer AEMO Electricity Market Notice 119033

Auto-generated on behalf of Manager NEM Real Time Operations
     
119041RECLASSIFY CONTINGENCY18/10/2024 08:53:53 PM

Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Duration: 18/10/2024 20:53 until further notice

Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Auto-generated on behalf of Manager NEM Real Time Operations
     
119040RECLASSIFY CONTINGENCY18/10/2024 07:34:23 PM

Cancellation of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Cancellation time: 18/10/2024 19:34

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 119037

Auto-generated on behalf of Manager NEM Real Time Operations
     
119039RECLASSIFY CONTINGENCY18/10/2024 07:04:22 PM

Cancellation of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Cancellation time: 18/10/2024 19:04

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 119035

Auto-generated on behalf of Manager NEM Real Time Operations
     