Filter by category
Filter by Date
[EventId:202403241205_review] Prices for interval 24-Mar-2024 12:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1200 hrs on 24 March 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Mar-2024 12:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202403241200_review] Prices for interval 24-Mar-2024 12:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1155 hrs on 24 March 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Mar-2024 12:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202403241155_review] Prices for interval 24-Mar-2024 11:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1150 hrs on 24 March 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 24-Mar-2024 11:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202403151600_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 15 March 2024 16:00
Issued by Australian Energy Market Operator Ltd at 1600 hrs on 15 March 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 March 2024.
Refer to market notice: 115646
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1600 hrs on 15 March 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202403151410_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 15 March 2024 14:10
Issued by Australian Energy Market Operator Ltd at 1410 hrs on 15 March 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 March 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1410 hrs on 15 March 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202403151400_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 15 March 2024 14:00
Issued by Australian Energy Market Operator Ltd at 1400 hrs on 15 March 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 March 2024.
Refer to market notice: 115643
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1400 hrs on 15 March 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202403151305_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 15 March 2024 13:05
Issued by Australian Energy Market Operator Ltd at 1305 hrs on 15 March 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 March 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1305 hrs on 15 March 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202403151230_review] Prices for interval 15-Mar-2024 12:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1225 hrs on 15 March 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 15-Mar-2024 12:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202403151225_review] Prices for interval 15-Mar-2024 12:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1220 hrs on 15 March 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 15-Mar-2024 12:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.