Market Notices

113061SETTLEMENTS RESIDUE05/01/2024 01:30:22 PM

[EventId:202401051330_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 05 January 2024 13:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 5 January 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 5 January 2024.

Refer to market notice: 113060

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1330 hrs on 5 January 2024.

This is an AEMO autogenerated Market Notice.
113060SETTLEMENTS RESIDUE05/01/2024 12:35:29 PM

[EventId:202401051235_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 05 January 2024 12:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1235 hrs on 5 January 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 5 January 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1235 hrs on 5 January 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
113057MARKET INTERVENTION05/01/2024 10:04:15 AM

Possible intervention to manage power system security in SA Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA Region

The synchronous generating units currently expected to be synchronised in SA from 0200 hrs 06/01/2024 will be inadequate to maintain a secure operating state in SA.

AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
113054MARKET INTERVENTION04/01/2024 06:04:11 PM

Update - Direction - SA Region - 03/01/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 03/01/2024

Refer Market Notice 113010

The AEMO intervention event that commenced from interval ending 1005 hrs on 03/01/2024 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
113013INTER-REGIONAL TRANSFER03/01/2024 12:32:13 PM

Inter-regional transfer limit variation - South Pine SVC - QLD region - 03/01/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - South Pine SVC - QLD region - 03/01/2024

At 1220 hrs 03/01/2024 there was an unplanned outage of the South Pine SVC.

The following constraint set(s) invoked at 1230 hrs 03/01/2024
Q-SP_VC

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
113010MARKET INTERVENTION03/01/2024 09:59:23 AM

Direction - SA region 03/01/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 03/01/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1005 hrs on 03/01/2024.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
113008INTER-REGIONAL TRANSFER03/01/2024 09:56:40 AM

Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)

AEMO ELECTRICITY MARKET NOTICE

Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region).

Refer AEMO Electricity Market Notice 113007

AEMO has been notified that the controls to vary Directlink output are now available.

Constraint set I-CTRL_ISSUE_TE revoked at 0940 hrs.

Manager NEM Real Time Operations
113007INTER-REGIONAL TRANSFER03/01/2024 09:25:47 AM

Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)

AEMO has been notified that the controls to vary Directlink output are unavailable until further notice.

Constraint set I-CTRL_ISSUE_TE invoked from 0920 hrs.

The constraint set contains equations with the following interconnector on the LHS:

N-Q-MNSP1


Manager NEM Real Time Operations
113006INTER-REGIONAL TRANSFER03/01/2024 08:52:51 AM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 1 Leg of Directlink .

The following constraint set was invoked at 0845 hrs 03/01/2024

N-X_MBTE_2

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations