Market Notices

114880INTER-REGIONAL TRANSFER19/02/2024 02:31:03 PM

Inter-regional transfer limit variation -Directlink DC2 - NSW region - 19/02/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Directlink DC2 - NSW region - 19/02/2024


A planned outage of Directlink DC2 in the NSW region was scheduled from 2000 hrs 16/02/2024 to 1701 hrs 20/02/2024.

The outage has been completed and Directlink DC2 returned to service at 1425 hrs 19/02/2024.

The following constraint set(s) revoked at 1425 hrs 19/02/2024
N-MBTE_1

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
114827INTER-REGIONAL TRANSFER16/02/2024 08:17:01 PM

Short Notice Outage - Directlink - NSW Region - 16 February 2024

AEMO ELECTRICITY MARKET NOTICE

Short Notice Outage - Directlink - NSW Region - 16 February 2024

A short notice outage of Directlink cable DC2 in the NSW Region.

Constraint set N-MBTE_1 invoked from 2010 hrs.

The constraint set contains equations with the following interconnector on the LHS:

N-Q-MNSP1

Refer to AEMO Network Outage Scheduler (NOS) for further details.


Manager NEM Real Time Operations
114810INTER-REGIONAL TRANSFER16/02/2024 02:44:54 PM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of all three legs of Directlink .

The following constraint set was invoked at 1440 hrs 16/02/2024

N-X_MBTE_3

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
114800PRICES SUBJECT TO REVIEW16/02/2024 01:50:20 PM

[EventId:202402161355_review] Prices for interval 16-Feb-2024 13:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1350 hrs on 16 February 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 16-Feb-2024 13:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
114799PRICES SUBJECT TO REVIEW16/02/2024 01:45:24 PM

[EventId:202402161350_review] Prices for interval 16-Feb-2024 13:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1345 hrs on 16 February 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 16-Feb-2024 13:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
114798PRICES SUBJECT TO REVIEW16/02/2024 01:40:18 PM

[EventId:202402161345_review] Prices for interval 16-Feb-2024 13:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1340 hrs on 16 February 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 16-Feb-2024 13:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
114797PRICES SUBJECT TO REVIEW16/02/2024 01:35:15 PM

[EventId:202402161340_review] Prices for interval 16-Feb-2024 13:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1335 hrs on 16 February 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 16-Feb-2024 13:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
114796PRICES SUBJECT TO REVIEW16/02/2024 01:30:22 PM

[EventId:202402161335_review] Prices for interval 16-Feb-2024 13:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 16 February 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 16-Feb-2024 13:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
114795PRICES SUBJECT TO REVIEW16/02/2024 01:25:17 PM

[EventId:202402161330_review] Prices for interval 16-Feb-2024 13:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1325 hrs on 16 February 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 16-Feb-2024 13:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.