114019RESERVE NOTICE30/01/2024 03:16:29 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113978 has been updated at 1400 hrs 30/01/2024 to the following:

1. From 1430 hrs to 1630 hrs 05/02/2024.
The forecast capacity reserve requirement is 1534 MW.
The minimum capacity reserve available is 869 MW.

2. From 1700 hrs to 2130 hrs 05/02/2024.
The forecast capacity reserve requirement is 1762 MW.
The minimum capacity reserve available is 1032 MW.

AEMO Operations
114017RESERVE NOTICE30/01/2024 03:17:27 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 04/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113976 has been updated at 1400 hrs 30/01/2024 to the following:

From 1700 hrs to 1930 hrs 04/02/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1174 MW.

AEMO Operations
114016RESERVE NOTICE30/01/2024 03:15:26 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 06/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1700 hrs to 1900 hrs 06/02/2024.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 476 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
114012MARKET SYSTEMS30/01/2024 01:47:21 PM

CHG0082787 | Completed | Pre-Production | Pre-Production MSATS r50.0.5 Patch Release

Change Number: CHG0082787

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)

Change Title: Pre-Production MSATS r50.0.5 Patch Release

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
113980RESERVE NOTICE29/01/2024 03:39:05 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 01/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113977 is cancelled at 1500 hrs 29/01/2024.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
113979RESERVE NOTICE29/01/2024 03:22:26 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 05/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1830 hrs to 1900 hrs 05/02/2024.
The forecast capacity reserve requirement is 1254 MW.
The minimum capacity reserve available is 1187 MW.

AEMO Operations
113978RESERVE NOTICE29/01/2024 03:13:45 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1430 hrs to 2200 hrs 05/02/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 730 MW.

AEMO Operations
113977RESERVE NOTICE29/01/2024 03:20:32 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 01/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113968 has been updated at 1400 hrs 29/01/2024 to the following:

From 0800 hrs to 1400 hrs 01/02/2024.
The forecast capacity reserve requirement is 910 MW.
The minimum capacity reserve available is 29 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
113976RESERVE NOTICE29/01/2024 03:10:28 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 04/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113912 has been updated at 1400 hrs 29/01/2024 to the following:

From 1700 hrs to 2130 hrs 04/02/2024.
The forecast capacity reserve requirement is 1489 MW.
The minimum capacity reserve available is 1108 MW.

AEMO Operations