117545NON-CONFORMANCE04/08/2024 06:30:18 AM

NON-CONFORMANCE Region QLD1 Sunday, 4 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 4 August 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: W/HOE#2
Duration: 04/08/2024 06:25 to 04/08/2024 06:30
Amount: -165 MW
Constraint: NC-Q_W/HOE#2

Auto-generated on behalf of Manager NEM Real Time Operations
     
117542NON-CONFORMANCE03/08/2024 04:35:17 PM

NON-CONFORMANCE Region NSW1 Saturday, 3 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 3 August 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BW03
Duration: 03/08/2024 16:25 to 03/08/2024 16:35
Amount: 72 MW
Constraint: NC-N_BW03

Auto-generated on behalf of Manager NEM Real Time Operations
     
117539NON-CONFORMANCE02/08/2024 06:15:12 PM

NON-CONFORMANCE Region SA1 Friday, 2 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Friday, 2 August 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: TB2BG1, TB2BL1
Aggregate Dispatch Group: TB2HYB_ADG1
Duration: 02/08/2024 12:10 to 02/08/2024 18:15
Amount: 14 MW
Constraint: NC-S_TB2HYB_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
     
117537MARKET INTERVENTION02/08/2024 02:48:59 PM

Cancellation - AEMO Intervention Event - SA region 01/08/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 01/08/2024

Refer to Market Notice 117525

The AEMO Intervention Event and all associated directions are cancelled from 1430 hrs on 02/08/2024.



Manager NEM Real Time Operations
     
117536MARKET INTERVENTION02/08/2024 02:38:20 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 117529

Direction is cancelled from: 1430 hrs 02/08/2024

Manager NEM Real Time Operations
     
117535MARKET INTERVENTION02/08/2024 12:49:55 PM

Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS

Refer to Market Notice 117526

Direction is cancelled from: 1230 hrs 02/08/2024

Manager NEM Real Time Operations
     
117534MARKET SYSTEMS02/08/2024 12:33:09 PM

CHG0091753 | Pre-Production | Pre production Gas Supply Hub (GSH) Environment Outage

Change Number: CHG0091753

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Gas Supply Hub

Change Title: Pre production Gas Supply Hub (GSH) Environment Outage

Change Start Date & Time: 08/08/2024 09:00:00 AEST

Change End Date & Time: 09/08/2024 17:00:00 AEST

Outage Start Date & Time: 08/08/2024 09:00:00 AEST

Outage End Date & Time: 09/08/2024 14:00:00 AEST

Environment: Pre-Production

Participant Impact and Requirements: "The AEMO Pre-production Gas Supply Hub (GSH) environment will be refreshed (GSH databases) and system will be unavailable during the outage window.

Access to Gas Suuply Hub (GSH) Trayport interface, GSH Day Ahead auction (DAA) and Pipeline capacity trading API and GSH web portal interfaces will be unavailable.

Upon completion of the outage users will be required to log in to pre-prod Gas Supply Hub Tray-port application using their production credentials as Trayport passwords in Pre-Production environment will be replaced with their Production passwords."

Support Information:

Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .
     
117533MARKET SYSTEMS02/08/2024 11:38:35 AM

CHG0093394 | Pre-Production | Planned Outage for the Gas Short Term Trading Market Systems SWEXIE Pre-Production.

Change Number: CHG0093394

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: STTM - Market Inputs - Manual

Change Title: Planned Outage for the Gas Short Term Trading Market Systems
SWEXIE Pre-Production.

Change Start Date & Time: 06/08/2024 18:30:00 AEST

Change End Date & Time: 06/08/2024 19:00:00 AEST

Outage Start Date & Time:

Outage End Date & Time:

Environment: Pre-Production

Participant Impact and Requirements: Gas Short Term Trading Market (STTM) SWEXIE services will not be available during the outage window in Pre-Production.

Support Information:

Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .
     
117532MARKET INTERVENTION02/08/2024 12:53:59 AM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 117531

Direction is cancelled from: 0105 hrs 02/08/2024

Manager NEM Real Time Operations
     