117669INTER-REGIONAL TRANSFER14/08/2024 08:05:49 AM

Inter-regional transfer limit variation - Collector - Marulan No 4 330kV Line - NSW region - 14/08/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Collector - Marulan No 4 330kV Line - NSW region - 14/08/2024

A planned outage of Collector - Marulan No 4 330kV Line in the NSW region was scheduled from 0800 hrs 14/08/2024 to 1700 hrs 02/09/2024.


The outage has been cancelled.

Constraint set(s) invoked: N-CTMN_4_WG_CLOSE


Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
117562RESERVE NOTICE05/08/2024 07:17:58 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 05/08/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 117561 is cancelled at 1915 hrs 05/08/2024.

Manager NEM Real Time Operations
     
117561RESERVE NOTICE05/08/2024 06:21:59 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 05/08/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 117548 has been updated at 1815 hrs to the following:

[1.] From 1930 hrs 05/08/2024 to 2130 hrs 05/08/2024.
The forecast capacity reserve requirement is 450 MW.
The minimum capacity reserve available is 386 MW.

Manager NEM Real Time Operations
     
117547RESERVE NOTICE05/08/2024 04:27:39 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 05/08/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

[1.] From 1900 hrs 05/08/2024 to 2200 hrs 05/08/2024.
The forecast capacity reserve requirement is 450 MW.
The minimum capacity reserve available is 317 MW.

Manager NEM Real Time Operations
     
117546INTER-REGIONAL TRANSFER04/08/2024 10:56:12 AM

Inter-regional transfer limit variation - Keilor to Sth Morang 500kV Line - VIC region - 04/08/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Keilor to Sth Morang 500kV Line - VIC region - 04/08/2024

A planned outage of Keilor to Sth Morang 500kV Line in the VIC region was scheduled from 1000 hrs 04/08/2024 to 1300 hrs 04/08/2024.

The outage has been completed and Keilor to Sth Morang 500kV Line returned to service at 1050 hrs 04/08/2024

Constraint set(s) revoked: V-KTSM_R

Manager NEM Real Time Operations
     
117501RESERVE NOTICE29/07/2024 05:49:35 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region [beginning] on 29/07/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 117497 is cancelled at 0545 hrs 29/07/2024.

Manager NEM Real Time Operations
     
117499RESERVE NOTICE28/07/2024 02:51:28 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 31/07/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 117493 is cancelled at 1420 hrs 28/07/2024

No LOR condition is currently forecast in the STPASA period.

Manager NEM Real Time Operations
     
117498RESERVE NOTICE28/07/2024 02:49:38 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 30/07/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 117492 is cancelled at 1420 hrs 28/07/2024

No LOR condition is currently forecast in the STPASA period.

Manager NEM Real Time Operations
     
117497RESERVE NOTICE28/07/2024 12:50:02 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 29/07/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following Period:

[1.] From 0730 hrs 29/07/2024 to 0830 hrs 29/07/2024.
The forecast capacity reserve requirement is 557 MW.
The minimum capacity reserve available is 517 MW.