Market Notices

117909POWER SYSTEM EVENTS28/08/2024 02:17:12 AM

Update - Non-credible contingency event - VIC region - 28/08/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - VIC region - 28/08/2024

Refer AEMO Electricity Market Notice 117908

At 0134 hrs the APD No 2 Potline was returned to service.

At 0200 hrs the APD No 1 Potline was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     
117908POWER SYSTEM EVENTS28/08/2024 01:02:22 AM

Non-credible contingency event - VIC region - 28/08/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - VIC region - 28/08/2024

At 0001 hrs the APD No1 Potline and the APD No 2 Potline tripped.

AEMO did not instruct load shedding.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
117907RECLASSIFY CONTINGENCY27/08/2024 11:51:21 PM

Reclassification of a Non-Credible Contingency Event: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: SA

Lines: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines

Duration: 27/08/2024 23:50 until further notice
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
     
117897PRICES SUBJECT TO REVIEW27/08/2024 04:00:19 PM

[EventId:202408271605_review] Prices for interval 27-Aug-2024 16:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1600 hrs on 27 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Aug-2024 16:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
117896PRICES SUBJECT TO REVIEW27/08/2024 03:55:24 PM

[EventId:202408271600_review] Prices for interval 27-Aug-2024 16:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1555 hrs on 27 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Aug-2024 16:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
117895PRICES SUBJECT TO REVIEW27/08/2024 03:50:24 PM

[EventId:202408271555_review] Prices for interval 27-Aug-2024 15:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1550 hrs on 27 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Aug-2024 15:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
117894MARKET INTERVENTION27/08/2024 03:53:44 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Market Notice 117812

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1830 hrs 28/08/2024.

The direction update is issued at 1600 hrs 27/08/2024.

Manager NEM Real Time Operations
     
117893PRICES SUBJECT TO REVIEW27/08/2024 03:45:22 PM

[EventId:202408271550_review] Prices for interval 27-Aug-2024 15:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1545 hrs on 27 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Aug-2024 15:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
117892MARKET INTERVENTION27/08/2024 03:52:35 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer AEMO Electricity Market Notice 117811

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 29/08/2024.

The direction update is issued at 1600 hrs 27/08/2024.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm