Update - Foreseeable AEMO intervention in SA region
Update - Foreseeable AEMO intervention in SA region
Refer AEMO Electricity Market Notice 117512
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 1000 hrs 01/08/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 1700 hrs 31/07/2024, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 1000 hrs 01/08/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Increase to QNI limit to next hold point of 1400 MW Qld to NSW
Refer to market notices 117060.
AEMO, TransGrid, Powerlink have reviewed the test results following the QNI minor testing on 19th June 2024. The next hold point can now be released.
The hold point of 1400 MW from Qld to NSW will be implemented as of 1000 hrs 31st July 2024.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
AEMO Operations
Update - Non-credible contingency event - QLD region - 30/07/2024
Update - Non-credible contingency event - QLD region - 30/07/2024
Refer AEMO Electricity Market Notice 117503
The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.
Region: QLD
Elements: Darling Downs Power Station
Duration: 0720 hrs until further notice
Constraint set(s) invoked: Q-DARLING_DOWNS_N-2
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region [beginning] on 29/07/2024
The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 117497 is cancelled at 0545 hrs 29/07/2024.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 31/07/2024
The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 117493 is cancelled at 1420 hrs 28/07/2024
No LOR condition is currently forecast in the STPASA period.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 30/07/2024
The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 117492 is cancelled at 1420 hrs 28/07/2024
No LOR condition is currently forecast in the STPASA period.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 29/07/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following Period:
[1.] From 0730 hrs 29/07/2024 to 0830 hrs 29/07/2024.
The forecast capacity reserve requirement is 557 MW.
The minimum capacity reserve available is 517 MW.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Heywood - South East No 2 275 kV Line - SA region - 26/07/2024
Inter-regional transfer limit variation -Heywood - South East No 2 275 kV Line SA region - 26/07/2024
A planned outage of Heywood - South East No 2 275 kV Line in the SA region was scheduled from 0830 hrs 26/07/2024 to 1730 hrs 28/07/2024.
The outage has been extended until 1200 hrs 29/07/2024
Constraint set(s) invoked:
I-HYSE
I-VS_050
I-VS+LKB_050
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations