Market Notices

117443RESERVE NOTICE25/07/2024 03:08:03 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 31/07/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following period:

From 0800 hrs to 0900 hrs 31/07/2024.
The forecast capacity reserve requirement is 555 MW.
The minimum capacity reserve available is 524 MW.

AEMO Operations
     
117442RESERVE NOTICE25/07/2024 03:06:45 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 29/07/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following period:

From 0730 hrs to 0900 hrs 29/07/2024.
The forecast capacity reserve requirement is 555 MW.
The minimum capacity reserve available is 524 MW.

AEMO Operations
     
117428NON-CONFORMANCE24/07/2024 08:55:12 AM

NON-CONFORMANCE Region QLD1 Wednesday, 24 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 24 July 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 24/07/2024 07:10 to 24/07/2024 08:55
Amount: -20 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
117427NON-CONFORMANCE23/07/2024 06:15:20 PM

NON-CONFORMANCE Region NSW1 Tuesday, 23 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 23 July 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: SHGEN
Duration: 23/07/2024 18:05 to 23/07/2024 18:15
Amount: -81 MW
Constraint: NC-N_SHGEN

Auto-generated on behalf of Manager NEM Real Time Operations
     
117412MARKET SYSTEMS22/07/2024 09:52:44 AM

CHG0090458 | Completed | Production | Planned Maintenance to Brisbane Internet firewall.

Change Number: CHG0090458
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Internet Access
Change Title: Planned Maintenance to Brisbane Internet firewall.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
117411INTER-REGIONAL TRANSFER22/07/2024 09:50:31 AM

Inter-regional transfer limit variation - Heywood - South East 1 275 kV Line - SA region - 22/07/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Heywood - South East 1 275 kV Line - SA region - 22/07/2024

A planned outage of Heywood - South East 1 275 kV Line in the SA region was scheduled from 0930 hrs 22/07/2024 to 1700 hrs 22/07/2024.

The outage has been cancelled.

Constraint set(s) revoked:
I-HYSE
I-VS+LKB_050
I-VS_050
S-SECB6611_10
S-SE_1CP

Manager NEM Real Time Operations
     
117403MARKET SYSTEMS21/07/2024 02:12:21 PM

CHG0091275 | Completed | Production | MSATS - eMDM Maintenance AKS v1.28 upgrade

Change Number: CHG0091275
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: MSATS - eMDM Maintenance AKS v1.28 upgrade
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
117389INTER-REGIONAL TRANSFER20/07/2024 02:52:46 PM

Inter-regional transfer limit variation - Armidale Coffs Harbour 96C 132kV LINE - NSW region - 20/07/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Armidale Coffs Harbour 96C 132kV LINE - NSW region - 20/07/2024

At 1422 hrs 20/07/2024 there was an unplanned outage of Armidale Coffs Harbour 96C 132kV LINE.

The following constraint set(s) invoked at 1430 hrs 20/07/2024
N-ARCH_96C

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
117387NON-CONFORMANCE20/07/2024 01:50:15 PM

NON-CONFORMANCE Region QLD1 Saturday, 20 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 20 July 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GANGARR1
Duration: 20/07/2024 12:20 to 20/07/2024 13:50
Amount: 60 MW
Constraint: NC-Q_GANGARR1

Auto-generated on behalf of Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm