118681PRICES SUBJECT TO REVIEW08/10/2024 03:50:13 PM

[EventId:202410081555_review] Prices for interval 08-Oct-2024 15:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1550 hrs on 8 October 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 08-Oct-2024 15:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118680PRICES SUBJECT TO REVIEW08/10/2024 03:45:16 PM

[EventId:202410081550_review] Prices for interval 08-Oct-2024 15:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1545 hrs on 8 October 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 08-Oct-2024 15:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118679PRICES SUBJECT TO REVIEW08/10/2024 03:40:17 PM

[EventId:202410081545_review] Prices for interval 08-Oct-2024 15:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1540 hrs on 8 October 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 08-Oct-2024 15:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118677MARKET INTERVENTION08/10/2024 02:18:21 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 118649

Direction is cancelled from: 1400 hrs 08/10/2024

Manager NEM Real Time Operations
     
118675MARKET INTERVENTION08/10/2024 03:41:42 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118650

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1530 hrs 09/10/2024.

The direction update is issued at 1600 hrs 8/10/2024.

Manager NEM Real Time Operations6
     
118672CONSTRAINTS08/10/2024 01:13:36 PM

Managing outages that create a credible risk of SA islanding

AEMO ELECTRICITY MARKET NOTICE

From 9th Oct 2024 AEMO will change constraints used during outages that create a credible risk of SA islanding.

From this date AEMO will:

1) Increase the maximum allowable flow on the V-SA interconnector from 50 MW to 250 MW in the VIC to SA direction, where the transmission outages is a planned outage.

2) Operate the SA region to the default 49-51 Hz target frequency containment band following a contingency event resulting in actual SA islanding. In order to meet this requirement, AEMO may now procure Contingency Raise FCAS locally from the SA region during these outages.

These changes reflect updated advice received by AEMO from the SA Jurisdictional System Security Coordinator.

The first network outage affected by this change is planned for 14th October 2024.

Andrew Groom
AEMO Operations
     
118668NON-CONFORMANCE08/10/2024 10:05:23 AM

NON-CONFORMANCE Region NSW1 Tuesday, 8 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 8 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BW04
Duration: 08/10/2024 10:00 to 08/10/2024 10:05
Amount: -37 MW
Constraint: NC-N_BW04

Auto-generated on behalf of Manager NEM Real Time Operations
     
118663NON-CONFORMANCE07/10/2024 03:12:48 PM

NON-CONFORMANCE Region VIC1 Monday, 7 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Monday, 7 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: STOCKYD1
Duration: 07/10/2024 13:25 to 07/10/2024 15:10
Amount: 62 MW
Constraint: NC-V_STOCKYD1

Auto-generated on behalf of Manager NEM Real Time Operations
     
118656PRICES SUBJECT TO REVIEW07/10/2024 03:00:24 PM

[EventId:202410071505_review] Prices for interval 07-Oct-2024 15:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1500 hrs on 7 October 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 07-Oct-2024 15:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm