118642RESERVE NOTICE07/10/2024 01:15:46 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Periods:

[1.] From 1700 hrs 08/10/2024 to 1730 hrs 08/10/2024.
The forecast capacity reserve requirement is 1147 MW.
The minimum capacity reserve available is 904 MW.

[2.] From 1900 hrs 08/10/2024 to 2200 hrs 08/10/2024.
The forecast capacity reserve requirement is 1187 MW.
The minimum capacity reserve available is 731 MW.

Manager NEM Real Time Operations
     
118641SETTLEMENTS RESIDUE07/10/2024 12:30:29 PM

[EventId:202410071230_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 07 October 2024 12:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1230 hrs on 7 October 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 7 October 2024.

Refer to market notice: 118640

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1230 hrs on 7 October 2024.

This is an AEMO autogenerated Market Notice.
     
118640SETTLEMENTS RESIDUE07/10/2024 11:35:25 AM

[EventId:202410071135_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 07 October 2024 11:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1135 hrs on 7 October 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 7 October 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1135 hrs on 7 October 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
118633MARKET INTERVENTION06/10/2024 02:29:16 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118611

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 08/10/2024.

The direction update is issued at 1430 hrs 06/10/2024.

Manager NEM Real Time Operations
     
118632MARKET INTERVENTION06/10/2024 02:28:09 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118610

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 08/10/2024.

The direction update is issued at 1430 hrs 06/10/2024.

Manager NEM Real Time Operations
     
118630RESERVE NOTICE06/10/2024 01:17:25 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 07/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 118629 is cancelled at 1314 hrs 06/10/2024.

Manager NEM Real Time Operations
     
118629RESERVE NOTICE06/10/2024 12:56:44 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 07/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:

[1.] From 1730 hrs 07/10/2024 to 1930 hrs 07/10/2024.
The forecast capacity reserve requirement is 1108 MW.
The minimum capacity reserve available is 963 MW.

Manager NEM Real Time Operations
     
118611MARKET INTERVENTION05/10/2024 03:01:42 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118595

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 07/10/2024.

The direction update is issued at 1500 hrs 05/10/2024.

Manager NEM Real Time Operations
     
118610MARKET INTERVENTION05/10/2024 03:00:31 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118594

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 07/10/2024.

The direction update is issued at 1500 hrs 05/10/2024.