Filter by category
Filter by Date
[EventId:202411101040_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 10 November 2024 10:40
Issued by Australian Energy Market Operator Ltd at 1040 hrs on 10 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 10 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1040 hrs on 10 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 120193
Direction is cancelled from: 1630 hrs 09/11/2024
Manager NEM Real Time Operations
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 120101
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Synergen Power Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS at 1600 hrs 09/11/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0700 hrs 10/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1700 hrs 10/11/2024 / further notice.
Synergen Power Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 120161
The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 11/11/2024.
The direction update is issued at 1600 hrs 09/11/2024.
Manager NEM Real Time Operations
Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS
Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer AEMO Electricity Participant Notice 120192
The MINTARO MINTARO GAS direction is now expected to commence at 1030 hrs 09/11/2024.
The direction update is issued at 0945 hrs 09/11/2024.
Manager NEM Real Time Operations
Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS
Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer AEMO Electricity Participant Notice 120164
The MINTARO MINTARO GAS direction is now expected to commence at 1000 hrs 09/11/2024.
The direction update is issued at 0750 hrs 09/11/2024.
Manager NEM Real Time Operations
[EventId:202411090715_confirmed] Prices for interval 09-Nov-2024 07:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0735 hrs on 9 November 2024
PRICES ARE NOW CONFIRMED for trading interval 09-Nov-2024 07:15.
In accordance with Market Notice 120181 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411090735_confirmed] Prices for interval 09-Nov-2024 07:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0735 hrs on 9 November 2024
PRICES ARE NOW CONFIRMED for trading interval 09-Nov-2024 07:35.
In accordance with Market Notice 120185 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411090730_confirmed] Prices for interval 09-Nov-2024 07:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0735 hrs on 9 November 2024
PRICES ARE NOW CONFIRMED for trading interval 09-Nov-2024 07:30.
In accordance with Market Notice 120184 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.