118615PRICES SUBJECT TO REVIEW05/10/2024 04:15:18 PM

[EventId:202410051620_review] Prices for interval 05-Oct-2024 16:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1615 hrs on 5 October 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Oct-2024 16:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118614PRICES SUBJECT TO REVIEW05/10/2024 04:10:24 PM

[EventId:202410051615_review] Prices for interval 05-Oct-2024 16:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1610 hrs on 5 October 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Oct-2024 16:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118613PRICES SUBJECT TO REVIEW05/10/2024 04:05:23 PM

[EventId:202410051610_review] Prices for interval 05-Oct-2024 16:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1605 hrs on 5 October 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Oct-2024 16:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118612PRICES SUBJECT TO REVIEW05/10/2024 04:00:25 PM

[EventId:202410051605_review] Prices for interval 05-Oct-2024 16:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1600 hrs on 5 October 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Oct-2024 16:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118611MARKET INTERVENTION05/10/2024 03:01:42 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118595

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 07/10/2024.

The direction update is issued at 1500 hrs 05/10/2024.

Manager NEM Real Time Operations
     
118610MARKET INTERVENTION05/10/2024 03:00:31 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118594

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 07/10/2024.

The direction update is issued at 1500 hrs 05/10/2024.

Manager NEM Real Time Operations
     
118598MARKET SYSTEMS04/10/2024 04:07:21 PM

CHG0098496 | Production | QLD Marketnet Router Replacement

Change Number: CHG0098496
Notification issued to: Market Notice
Notification Type: Initial

Change Type: Normal
Service/ Component: Market Network

Change Title: QLD Marketnet Router Replacement
Change Start Date & Time: 19/10/2024 14:00:53 AEST
Change End Date & Time: 19/10/2024 19:00:53 AEST

Outage Start Date & Time:
Outage End Date & Time:
Environment: Production

Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage on the 19th October 2024:

IPWAN Participants - A brief interuption of up to 60 seconds while services are failover from QLD to NSW Datacenter.

Lan-2-Lan VPN Participants (IPSEC) - Up to 2 hour outage for participants who have established their VPN connection/s via the AEMO QLD datacenter termination point (202.44.76.10) only - All L2L connections should be established to both QLD / NSW.

Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO NSW datacenter termination point (202.44.78.10) prior to this scheduled outage.

B2B VPN - No impact is expected.

SSL VPN Participants: None expected as SSL VPN's are hosted on a different device.

GASHUB: No impact is expected as GASHUB will be failed over to the NSW Datacenter.

Other Impacts will have been communicated in advance.

** FAILURE TO ENSURE VPN FAILOVER WILL RESULT IN LOSS OF MARKETNET CONNECTIVITY **
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .


     
118595MARKET INTERVENTION04/10/2024 03:54:13 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118565

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 06/10/2024.

The direction update is issued at 1550 hrs 04/10/2024.

Manager NEM Real Time Operations
     
118594MARKET INTERVENTION04/10/2024 03:53:03 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118560

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 06/10/2024.

The direction update is issued at 1550 hrs 04/10/2024.