Market Notices

117894MARKET INTERVENTION27/08/2024 03:53:44 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Market Notice 117812

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1830 hrs 28/08/2024.

The direction update is issued at 1600 hrs 27/08/2024.

Manager NEM Real Time Operations
     
117892MARKET INTERVENTION27/08/2024 03:52:35 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer AEMO Electricity Market Notice 117811

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 29/08/2024.

The direction update is issued at 1600 hrs 27/08/2024.

Manager NEM Real Time Operations
     
117889MARKET SYSTEMS27/08/2024 03:33:37 PM

CHG0095127 | Completed | Pre-Production | Pre-Prod NEM Reform - RMI (Retail Market Improvements) MSATS and eMDM Release

Change Number: CHG0095127
Notification issued to: Market Notice
Notification Type: Completed

Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Prod NEM Reform - RMI (Retail Market Improvements) MSATS and eMDM Release

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
117888SETTLEMENTS RESIDUE27/08/2024 03:30:23 PM

[EventId:202408271530_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 27 August 2024 15:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1530 hrs on 27 August 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 27 August 2024.

Refer to market notice: 117877

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.

The negative residue constraint NRM_QLD1_NSW1 ceased operating at 1530 hrs on 27 August 2024.

This is an AEMO autogenerated Market Notice.
     
117877SETTLEMENTS RESIDUE27/08/2024 02:37:01 PM

[EventId:202408271435_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 27 August 2024 14:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1435 hrs on 27 August 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 27 August 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.

The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1435 hrs on 27 August 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
117875MARKET SYSTEMS27/08/2024 02:34:03 PM

CHG0096175 | Production | EMMS Production Bay transfer

Change Number: CHG0096175
Notification issued to: Market Notice
Notification Type: Initial

Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: EMMS Production Bay transfer

Change Start Date & Time: 02/09/2024 09:00:00 AEST
Change End Date & Time: 04/09/2024 16:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:

Environment: Production

Participant Impact and Requirements: EMMS Bay transfer is scheduled for 3rd September is not expected to have any impact. If any issues are identified because of this maintenance activity, please contact the AEMO Support Hub 1300 236 600.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.

Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities.

     
117848SETTLEMENTS RESIDUE27/08/2024 12:30:27 PM

[EventId:202408271230_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 27 August 2024 12:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1230 hrs on 27 August 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 27 August 2024.

Refer to market notice: 117834

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.

The negative residue constraint NRM_QLD1_NSW1 ceased operating at 1230 hrs on 27 August 2024.

This is an AEMO autogenerated Market Notice.
     
117834SETTLEMENTS RESIDUE27/08/2024 11:36:54 AM

[EventId:202408271135_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 27 August 2024 11:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1135 hrs on 27 August 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 27 August 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.

The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1135 hrs on 27 August 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
117818RECLASSIFY CONTINGENCY27/08/2024 05:36:33 AM

Reclassification of a Non-Credible Contingency Event: Para-Templers West and Magill-Torrens Island A 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: SA

Lines: Para-Templers West and Magill-Torrens Island A 275kV lines

Duration: 0530 hrs 27 Aug 2024 until further notice
Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
     