Market Notices

118626RESERVE NOTICE05/10/2024 10:35:54 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 08/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 118625 is cancelled at 2230 hrs 05/10/2024.

No LOR2 condition is currently forecast in the STPASA period.

Manager NEM Real Time Operations
     
118625RESERVE NOTICE05/10/2024 07:33:35 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 08/10/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period[s]:

[1.] From 1730 hrs 08/10/2024 to 1800 hrs 08/10/2024.
The forecast capacity reserve requirement is 799 MW.
The minimum capacity reserve available is 767 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
118598MARKET SYSTEMS04/10/2024 04:07:21 PM

CHG0098496 | Production | QLD Marketnet Router Replacement

Change Number: CHG0098496
Notification issued to: Market Notice
Notification Type: Initial

Change Type: Normal
Service/ Component: Market Network

Change Title: QLD Marketnet Router Replacement
Change Start Date & Time: 19/10/2024 14:00:53 AEST
Change End Date & Time: 19/10/2024 19:00:53 AEST

Outage Start Date & Time:
Outage End Date & Time:
Environment: Production

Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage on the 19th October 2024:

IPWAN Participants - A brief interuption of up to 60 seconds while services are failover from QLD to NSW Datacenter.

Lan-2-Lan VPN Participants (IPSEC) - Up to 2 hour outage for participants who have established their VPN connection/s via the AEMO QLD datacenter termination point (202.44.76.10) only - All L2L connections should be established to both QLD / NSW.

Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO NSW datacenter termination point (202.44.78.10) prior to this scheduled outage.

B2B VPN - No impact is expected.

SSL VPN Participants: None expected as SSL VPN's are hosted on a different device.

GASHUB: No impact is expected as GASHUB will be failed over to the NSW Datacenter.

Other Impacts will have been communicated in advance.

** FAILURE TO ENSURE VPN FAILOVER WILL RESULT IN LOSS OF MARKETNET CONNECTIVITY **
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .


     
118539MARKET SYSTEMS30/09/2024 05:41:19 PM

CHG0098133:NEM Reform - RMI (Retail Market Improvements) MSATS 54.0 - Completed

Change Number: CHG0098133
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Market Settlement & Transfer System
Change Title: NEM Reform - RMI (Retail Market Improvements) MSATS 54.0
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
118474RESERVE NOTICE26/09/2024 08:01:21 PM

Cancellation of Actual (LOR1) condition in the NSW region - 26/09/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 26/09/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.118473 is cancelled at 2000 hrs 26/09/2024.

Manager NEM Real Time Operations
     
118473RESERVE NOTICE26/09/2024 06:48:28 PM

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 26/09/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 26/09/2024

The Actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 118472 has been updated at 1850 hrs to the following:

The Actual LOR1 condition is forecast to exist until 2000 hrs.

The forecast capacity reserve requirement is 1420 MW.
The minimum capacity reserve available is 996 MW.

Manager NEM Real Time Operations
     
118472RESERVE NOTICE26/09/2024 06:15:18 PM

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 26/09/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 26/09/2024

The actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 118471 has been updated at 1815 hrs to the following:

The Actual LOR1 condition is forecast to exist until 2000 hrs.

The forecast capacity reserve requirement is 1420 MW.
The minimum capacity reserve available is 726 MW.

Manager NEM Real Time Operations
     
118471RESERVE NOTICE26/09/2024 04:41:23 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 26/09/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 26/09/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs

The capacity reserve requirement is 1440 MW
The minimum capacity reserve available is 1027 MW

Manager NEM Real Time Operations
     
118443MARKET SYSTEMS25/09/2024 02:43:56 PM

CHG0098660:Telstra Melbourne Indial (03 9609 XXXX-XXXX)

Change Number: CHG0098660
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Cisco IP Phone
Change Title: Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     