117514MARKET INTERVENTION31/07/2024 02:26:01 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 117512

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 1000 hrs 01/08/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1700 hrs 31/07/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
117513NON-CONFORMANCE31/07/2024 01:35:19 PM

NON-CONFORMANCE Region NSW1 Wednesday, 31 July 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 31 July 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BW01
Duration: 31/07/2024 13:30 to 31/07/2024 13:35
Amount: -17 MW
Constraint: NC-N_BW01

Auto-generated on behalf of Manager NEM Real Time Operations
     
117512MARKET INTERVENTION31/07/2024 12:39:56 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 1000 hrs 01/08/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
117511MARKET SYSTEMS31/07/2024 09:13:12 AM

CHG0091533 | Completed | Production | Planned Outage for the Gas Short Term Trading Market Systems Production.

Change Number: CHG0091533

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: Short Term Trading Market

Change Title: Planned Outage for the Gas Short Term Trading Market Systems Production.

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
117508GENERAL NOTICE30/07/2024 02:45:25 PM

Increase to QNI limit to next hold point of 1400 MW Qld to NSW

AEMO ELECTRICITY MARKET NOTICE

Refer to market notices 117060.

AEMO, TransGrid, Powerlink have reviewed the test results following the QNI minor testing on 19th June 2024. The next hold point can now be released.

The hold point of 1400 MW from Qld to NSW will be implemented as of 1000 hrs 31st July 2024.

Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade

Ben Blake
AEMO Operations
     
117507MARKET SYSTEMS30/07/2024 01:27:09 PM

CHG0091507 | Production | As part of the Platform Services Patching Program, webMethods Inactive Production Application Servers in Brisbane will have critical s

Change Number: CHG0091507

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: MSATS - Business to Business data exchange

Change Title: As part of the Platform Services Patching Program, webMethods Inactive Production Application Servers in Brisbane will have critical security patches applied.

Change Start Date & Time: 26/08/2024 08:00:00 AEST
Change End Date & Time: 28/08/2024 18:00:00 AEST

Outage Start Date & Time:
Outage End Date & Time:

Environment: Production

Participant Impact and Requirements: This is the Inactive Production environment, there is no impact for external participants.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .
     
117490MARKET INTERVENTION27/07/2024 03:00:51 PM

Cancellation - AEMO Intervention Event - SA region 26/07/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 26/07/2024

Refer to Market Notice 117472

The AEMO Intervention Event and all associated directions are cancelled from 1500 hrs on 27/07/2024.



Manager NEM Real Time Operations
     
117489MARKET INTERVENTION27/07/2024 02:59:32 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 117485

Direction is cancelled from: 1500 hrs 27/07/2024

Manager NEM Real Time Operations
     
117488MARKET INTERVENTION27/07/2024 01:59:58 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 117471

Direction is cancelled from: 1400 hrs 27/07/2024

Manager NEM Real Time Operations
     