Filter by category
Filter by Date
NON-CONFORMANCE Region VIC1 Saturday, 9 November 2024
NON-CONFORMANCE VIC1 Region Saturday, 9 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GANNB1
Duration: 09/11/2024 20:55 to 09/11/2024 21:10
Amount: 9 MW
Constraint: NC-V_GANNB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Saturday, 9 November 2024
NON-CONFORMANCE NSW1 Region Saturday, 9 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP5
Duration: 09/11/2024 02:40 to 09/11/2024 02:45
Amount: -42 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202411082115_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 08 November 2024 21:15
Issued by Australian Energy Market Operator Ltd at 2115 hrs on 8 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 November 2024.
Refer to market notice: 120165
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2115 hrs on 8 November 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202411081705_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 08 November 2024 17:05
Issued by Australian Energy Market Operator Ltd at 1705 hrs on 8 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1705 hrs on 8 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202411081430_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 08 November 2024 14:30
Issued by Australian Energy Market Operator Ltd at 1430 hrs on 8 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 November 2024.
Refer to market notice: 120143
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1430 hrs on 8 November 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202411081300_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 08 November 2024 13:00
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 8 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1300 hrs on 8 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region NSW1 Friday, 8 November 2024
NON-CONFORMANCE NSW1 Region Friday, 8 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 08/11/2024 12:30 to 08/11/2024 12:45
Amount: 16 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 8 November 2024
NON-CONFORMANCE NSW1 Region Friday, 8 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BHB1
Duration: 08/11/2024 09:15 to 08/11/2024 10:10
Amount: 25 MW
Constraint: NC-N_BHB1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202411081005_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 08 November 2024 10:05
Issued by Australian Energy Market Operator Ltd at 1005 hrs on 8 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 November 2024.
Refer to market notice: 120132
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1005 hrs on 8 November 2024.
This is an AEMO autogenerated Market Notice.