Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 117767
Direction is cancelled from: 1530 hrs 24/08/2024
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Saturday, 24 August 2024
NON-CONFORMANCE NSW1 Region Saturday, 24 August 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WYASF1
Duration: 24/08/2024 11:10 to 24/08/2024 11:20
Amount: 43 MW
Constraint: NC-N_WYASF1
Auto-generated on behalf of Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer AEMO Electricity Market Notice 117766
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1530 hrs 24/08/2024.
The direction update is issued at 1100 hrs 24/08/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer AEMO Electricity Market Notice 117762
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 25/08/2024.
The direction update is issued at 0830 hrs 24/08/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAND
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 117754
This update is issued at 1700 hrs 23/08/2024 and is expected to stay in place until 0400 hrs 25/08/2024
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer AEMO Electricity Market Notice 117758
This update is issued at 1700 hrs 23/08/2024 and is expected to stay in place until 1530 hrs 24/08/2024
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 23 August 2024
NON-CONFORMANCE NSW1 Region Friday, 23 August 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: CAPBES1G, CAPBES1L
Aggregate Dispatch Group: CBESS_ADG1
Duration: 23/08/2024 04:35 to 23/08/2024 05:00
Amount: 13 MW
Constraint: NC-N_CBESS_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-regional transfer limit variation - Dumaresq SVC - NSW region - 22/08/2024
Inter-regional transfer limit variation - Dumaresq SVC - NSW region - 22/08/2024
At 2238 hrs 22/08/2024 there was an unplanned of Dumaresq SVC
Constraint set(s) invoked: N-DM_SVC
The following constraint set(s) invoked at 2250 hrs 22/08/2024
N-DM_SVC
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAND
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 117755
TORRB2 TORRENS ISLAND synchronise time update.
Required actions: synchronise and follow dispatch targets at 0030 hrs 23/08/2024
This update is issued at 2030 hrs 22/08/2024 and is expected to stay in place until 0400 hrs 24/08/2024.
Manager NEM Real Time Operations