Market Notices

117782POWER SYSTEM EVENTS25/08/2024 09:24:53 AM

Non-credible contingency event - TAS region - 25/08/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 25/08/2024

At 0850 hrs the New Norfolk A 110kV Bus tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
117772NON-CONFORMANCE24/08/2024 11:20:24 AM

NON-CONFORMANCE Region NSW1 Saturday, 24 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 24 August 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WYASF1
Duration: 24/08/2024 11:10 to 24/08/2024 11:20
Amount: 43 MW
Constraint: NC-N_WYASF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
117760NON-CONFORMANCE23/08/2024 05:00:21 AM

NON-CONFORMANCE Region NSW1 Friday, 23 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 23 August 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: CAPBES1G, CAPBES1L
Aggregate Dispatch Group: CBESS_ADG1
Duration: 23/08/2024 04:35 to 23/08/2024 05:00
Amount: 13 MW
Constraint: NC-N_CBESS_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
     
117744NON-CONFORMANCE21/08/2024 10:00:14 PM

NON-CONFORMANCE Region QLD1 Wednesday, 21 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 21 August 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 21/08/2024 21:50 to 21/08/2024 22:00
Amount: 10 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
117692NON-CONFORMANCE15/08/2024 10:50:17 PM

NON-CONFORMANCE Region QLD1 Thursday, 15 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 15 August 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 15/08/2024 22:25 to 15/08/2024 22:50
Amount: -32 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
117687NON-CONFORMANCE15/08/2024 06:15:18 PM

NON-CONFORMANCE Region QLD1 Thursday, 15 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 15 August 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 15/08/2024 17:55 to 15/08/2024 18:15
Amount: -44 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
117680NON-CONFORMANCE15/08/2024 12:40:26 PM

NON-CONFORMANCE Region SA1 Thursday, 15 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Thursday, 15 August 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: TB2BG1, TB2BL1
Aggregate Dispatch Group: TB2HYB_ADG1
Duration: 15/08/2024 11:05 to 15/08/2024 12:40
Amount: -28 MW
Constraint: NC-S_TB2HYB_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
     
117679NON-CONFORMANCE15/08/2024 10:10:17 AM

NON-CONFORMANCE Region SA1 Thursday, 15 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Wednesday, 14 August 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: TB2BG1, TB2BL1
Aggregate Dispatch Group: TB2HYB_ADG1
Duration: 14/08/2024 15:50 to 15/08/2024 10:10
Amount: -28 MW
Constraint: NC-S_TB2HYB_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
     
117676NON-CONFORMANCE14/08/2024 03:20:18 PM

NON-CONFORMANCE Region SA1 Wednesday, 14 August 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Wednesday, 14 August 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: TB2BG1, TB2BL1
Aggregate Dispatch Group: TB2HYB_ADG1
Duration: 14/08/2024 10:30 to 14/08/2024 15:20
Amount: 26 MW
Constraint: NC-S_TB2HYB_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm