118624NON-CONFORMANCE05/10/2024 07:15:20 PM

NON-CONFORMANCE Region QLD1 Saturday, 5 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 5 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 05/10/2024 18:45 to 05/10/2024 19:15
Amount: 37 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
118617PRICES SUBJECT TO REVIEW05/10/2024 04:25:16 PM

[EventId:202410051630_review] Prices for interval 05-Oct-2024 16:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1625 hrs on 5 October 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Oct-2024 16:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118616PRICES SUBJECT TO REVIEW05/10/2024 04:20:13 PM

[EventId:202410051625_review] Prices for interval 05-Oct-2024 16:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1620 hrs on 5 October 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Oct-2024 16:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118615PRICES SUBJECT TO REVIEW05/10/2024 04:15:18 PM

[EventId:202410051620_review] Prices for interval 05-Oct-2024 16:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1615 hrs on 5 October 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Oct-2024 16:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118614PRICES SUBJECT TO REVIEW05/10/2024 04:10:24 PM

[EventId:202410051615_review] Prices for interval 05-Oct-2024 16:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1610 hrs on 5 October 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Oct-2024 16:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118613PRICES SUBJECT TO REVIEW05/10/2024 04:05:23 PM

[EventId:202410051610_review] Prices for interval 05-Oct-2024 16:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1605 hrs on 5 October 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Oct-2024 16:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118612PRICES SUBJECT TO REVIEW05/10/2024 04:00:25 PM

[EventId:202410051605_review] Prices for interval 05-Oct-2024 16:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1600 hrs on 5 October 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Oct-2024 16:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
118611MARKET INTERVENTION05/10/2024 03:01:42 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118595

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 07/10/2024.

The direction update is issued at 1500 hrs 05/10/2024.

Manager NEM Real Time Operations
     
118610MARKET INTERVENTION05/10/2024 03:00:31 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118594

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 07/10/2024.

The direction update is issued at 1500 hrs 05/10/2024.

Manager NEM Real Time Operations
     