NON-CONFORMANCE Region VIC1 Saturday, 9 November 2024
NON-CONFORMANCE VIC1 Region Saturday, 9 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GANNB1
Duration: 09/11/2024 20:55 to 09/11/2024 21:10
Amount: 9 MW
Constraint: NC-V_GANNB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Saturday, 9 November 2024
NON-CONFORMANCE NSW1 Region Saturday, 9 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP5
Duration: 09/11/2024 02:40 to 09/11/2024 02:45
Amount: -42 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 8 November 2024
NON-CONFORMANCE NSW1 Region Friday, 8 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 08/11/2024 12:30 to 08/11/2024 12:45
Amount: 16 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 8 November 2024
NON-CONFORMANCE NSW1 Region Friday, 8 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BHB1
Duration: 08/11/2024 09:15 to 08/11/2024 10:10
Amount: 25 MW
Constraint: NC-N_BHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 7 November 2024
NON-CONFORMANCE NSW1 Region Thursday, 7 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 07/11/2024 14:35 to 07/11/2024 15:05
Amount: -32 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 7 November 2024
NON-CONFORMANCE NSW1 Region Thursday, 7 November 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 07/11/2024 09:00 to 07/11/2024 10:45
Amount: -50 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 31 October 2024
NON-CONFORMANCE Region NSW1 Thursday, 31 October 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:.
Unit: MP1
Duration: 31/10/2024 13:25 to 31/10/2024 13:30
Amount: -52 MW
Constraint: NC-N_MP1
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 31 October 2024
NON-CONFORMANCE QLD1 Region Thursday, 31 October 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 31/10/2024 12:50 to 31/10/2024 13:05
Amount: 24 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
Update - Non-credible contingency event - NSW region - 31/10/2024
Update - Non-credible contingency event - NSW region - 31/10/2024
Refer AEMO Electricity Market Notice 119689
At 0345 hrs the Wagga B 330 kV bus was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations