Filter by category
Filter by Date
Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: NSW1
Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV
Cancellation time: 10/11/2024 15:29
Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
Refer AEMO Electricity Market Notice 120208
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202411101410_confirmed] Prices for interval 10-Nov-2024 14:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1430 hrs on 10 November 2024
PRICES ARE NOW CONFIRMED for trading interval 10-Nov-2024 14:10.
In accordance with Market Notice 120203 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411101430_confirmed] Prices for interval 10-Nov-2024 14:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1430 hrs on 10 November 2024
PRICES ARE NOW CONFIRMED for trading interval 10-Nov-2024 14:30.
In accordance with Market Notice 120207 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411101425_confirmed] Prices for interval 10-Nov-2024 14:25 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1430 hrs on 10 November 2024
PRICES ARE NOW CONFIRMED for trading interval 10-Nov-2024 14:25.
In accordance with Market Notice 120206 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411101420_confirmed] Prices for interval 10-Nov-2024 14:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1430 hrs on 10 November 2024
PRICES ARE NOW CONFIRMED for trading interval 10-Nov-2024 14:20.
In accordance with Market Notice 120205 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411101415_confirmed] Prices for interval 10-Nov-2024 14:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1430 hrs on 10 November 2024
PRICES ARE NOW CONFIRMED for trading interval 10-Nov-2024 14:15.
In accordance with Market Notice 120204 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202411101405_confirmed] Prices for interval 10-Nov-2024 14:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1430 hrs on 10 November 2024
PRICES ARE NOW CONFIRMED for trading interval 10-Nov-2024 14:05.
In accordance with Market Notice 120201 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: NSW1
Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV
Duration: 10/11/2024 14:25 until further notice
Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 120193
Direction is cancelled from: 1630 hrs 09/11/2024
Manager NEM Real Time Operations