Market Notices

117916INTER-REGIONAL TRANSFER28/08/2024 09:06:54 AM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 28/08/2024

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_SYDS_55E0E615 from 0900 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

N-Q-MNSP1

Refer to AEMO Network Outage Scheduler (NOS) for further information.

Manager NEM Real Time Operations
     
117832INTER-REGIONAL TRANSFER27/08/2024 11:05:19 AM

Cancellation - Inter-Regional Transfer limit variation - Murraylink 27/08/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Inter-Regional Transfer limit variation - Murraylink 27/08/2024

Refer AEMO Electricity Market Notice 117831

To manage power system security in the Victoria region, AEMO invoked the following network constraint.

Constraint Set invoked from 10:40 hrs 27/08/2024 to 11:00 hrs 27/08/2024
I:SVML_120

This constraint set contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Manager NEM Real Time Operations
     
117831INTER-REGIONAL TRANSFER27/08/2024 10:51:11 AM

Inter-Regional Transfer limit variation - Murraylink 27/08/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Murraylink 27/08/2024

To manage power system security in the Victoria region, AEMO has invoked the following network constraint.

Constraint Set invoked at 10:40 HRS 27/08/2024
I:SVML_120

This constraint set contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Manager NEM Real Time Operations
     
117806INTER-REGIONAL TRANSFER26/08/2024 03:08:55 AM

Inter-regional transfer limit variation - Cherry Gardens - Torrens Island B 275kV Line - SA region - 26/08/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Cherry Gardens - Torrens Island B 275kV Line - SA region - 26/08/2024

At 0250 hrs 26/08/2024 there was a short notice outage of Cherry Gardens - Torrens Island B 275kV Line.

The following constraint set(s) invoked at 0250 hrs 26/08/2024
S-CGTI

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
117781INTER-REGIONAL TRANSFER25/08/2024 08:10:50 AM

Inter-regional transfer limit variation -Redcliffs No 2 220 kV Bus - VIC region - 25/08/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation -Redcliffs No 2 220 kV Bus - VIC region - 25/08/2024

A planned outage of Redcliffs No 2 220 kV Bus in the VIC region was scheduled from 0630 hrs 25/08/2024 to 1730 hrs 25/08/2024.

The outage has been cancelled at 0805 hrs.

The following constraint set(s) were invoked
Constraint Sets: V-KMRC, V-RCTS220CAPAUTO

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,T-V-MNSP1,V-SA,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
117759INTER-REGIONAL TRANSFER22/08/2024 10:54:09 PM

Inter-regional transfer limit variation - Dumaresq SVC - NSW region - 22/08/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Dumaresq SVC - NSW region - 22/08/2024

At 2238 hrs 22/08/2024 there was an unplanned of Dumaresq SVC

Constraint set(s) invoked: N-DM_SVC

The following constraint set(s) invoked at 2250 hrs 22/08/2024
N-DM_SVC

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
117725INTER-REGIONAL TRANSFER20/08/2024 09:28:20 AM

Inter-regional transfer limit variation - Kerang to Wemen 220kV line - VIC region - 20/08/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Kerang to Wemen 220kV line - VIC region - 20/08/2024

A planned outage of Kerang to Wemen 220kV line in the VIC region was scheduled from 0600 hrs 20/08/2024 to 1930 hrs 20/08/2024.

The outage has been completed and Kerang to Wemen 220kV line returned to service at 0925 hrs 20/08/2024

Constraint set revoked: V-KGWT

Manager NEM Real Time Operations
     
117724INTER-REGIONAL TRANSFER19/08/2024 09:54:20 PM

Inter-Regional Transfer limit variation - Murraylink

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Murraylink

There has been an unplanned outage of the Murraylink interconnector.

The following constraint set was invoked at 2155 hrs 19/08/2024

I-MURRAYLINK

The constraint set contains the following interconnector on the left hand side.

V-S-MNSP1,VIC1-NSW1

Refer to AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
     
117677INTER-REGIONAL TRANSFER14/08/2024 04:22:12 PM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 1 Leg of Directlink .

The following constraint set was invoked at 1620 hrs 14/08/2024

N-MBTE_1

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm