118070INTER-REGIONAL TRANSFER02/09/2024 03:36:51 PM

Inter-regional transfer limit variation - Lismore-Lismore132 9W1 132kV Line - NSW region - 02/09/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Lismore-Lismore132 9W1 132kV Line - NSW region - 02/09/2024

At 1516 hrs 02/09/2024 there was an unplanned outage of Lismore-Lismore132 9W1 132kV Line

The following constraint set(s) invoked at 1525 hrs 02/09/2024
N-LSLS_9U8

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
118061INTER-REGIONAL TRANSFER02/09/2024 01:57:46 PM

Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 kV Line - NSW region - 02/09/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 kV Line - NSW region - 02/09/2024

A planned outage of Armidale - Sapphire 8E 330 kV Line in the NSW region was scheduled from 1630 hrs 31/08/2024 to 1800 hrs 02/09/2024.

The outage has been rescheduled for 1630 hrs 31/08/2024 to 1200 hrs 03/09/2024.

The following constraint set(s) invoked at 1630 hrs 31/08/2024
N-ARSR_8E, N-DM_SVC, N-TW_SVC

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,T-V-MNSP1,N-Q-MNSP1,V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
118052MARKET SYSTEMS02/09/2024 09:43:44 AM

CHG0091339 | Completed | Production | NSW Marketnet Router Replacement

Change Number: CHG0091339

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: Market Network

Change Title: NSW Marketnet Router Replacement

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
118037GENERAL NOTICE01/09/2024 09:29:36 PM

Network Augmentation Commissioned - NSW Region - 01/09/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - NSW Region - 01/09/2024

At 2125 hrs. Buronga -Redcliffs X9 220 kV line has been commissioned.
At 2125 hrs. Buronga -Redcliffs OX1 220 kV line has been de-commissioned.

Manager NEM Real Time Operations
     
118026INTER-REGIONAL TRANSFER01/09/2024 10:39:29 AM

Inter-regional transfer limit variation - Armidale - Sapphire 8E 330kv Line- NSW region - 01/09/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Armidale - Sapphire 8E 330kv Line - NSW region - 01/09/2024

A planned outage of Armidale - Sapphire 8E 330kv Line in the NSW region was scheduled from 1630 hrs 31/08/2024 to 0910 hrs 02/09/2024.

The outage has been rescheduled for 1630 hrs 31/08/2024 to 1800 hrs 02/09/2024.


The following constraint set(s) invoked at 1630 hrs 31/08/2024
N-ARSR_8E
N-TW_SVC
N-DM_SVC


This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,T-V-MNSP1,N-Q-MNSP1,V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
118016INTER-REGIONAL TRANSFER31/08/2024 04:31:20 PM

Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 kV line - NSW region - 31/08/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Armidale - Sapphire 8E 330 kV line - NSW region - 31/08/2024

At 1630 hrs 31/08/2024 there was a short notice outage of Armidale - Sapphire 8E 330 kV line.

The following constraint set(s) invoked at 1630 hrs 31/08/2024
N-ARSR_8E, N-TW_SVC

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,T-V-MNSP1,N-Q-MNSP1,V-S-MNSP1,V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
117975PRICES UNCHANGED29/08/2024 07:41:43 PM

[EventId:202408291910_confirmed] Prices for interval 29-Aug-2024 19:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1930 hrs on 29 August 2024

PRICES ARE NOW CONFIRMED for trading interval 29-Aug-2024 19:10.

In accordance with Market Notice 117962 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
117974PRICES UNCHANGED29/08/2024 07:39:19 PM

[EventId:202408291930_confirmed] Prices for interval 29-Aug-2024 19:30 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1930 hrs on 29 August 2024

PRICES ARE NOW CONFIRMED for trading interval 29-Aug-2024 19:30.

In accordance with Market Notice 117969 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
117973PRICES UNCHANGED29/08/2024 07:37:34 PM

[EventId:202408291925_confirmed] Prices for interval 29-Aug-2024 19:25 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1930 hrs on 29 August 2024

PRICES ARE NOW CONFIRMED for trading interval 29-Aug-2024 19:25.

In accordance with Market Notice 117968 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     