[EventId:202411101040_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 10 November 2024 10:40
Issued by Australian Energy Market Operator Ltd at 1040 hrs on 10 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 10 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1040 hrs on 10 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202411082115_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 08 November 2024 21:15
Issued by Australian Energy Market Operator Ltd at 2115 hrs on 8 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 November 2024.
Refer to market notice: 120165
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2115 hrs on 8 November 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202411081705_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 08 November 2024 17:05
Issued by Australian Energy Market Operator Ltd at 1705 hrs on 8 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1705 hrs on 8 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 08/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120138 is cancelled at 1510 hrs 08/11/2024.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/11/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 120139 is cancelled at 1545 hrs 08/11/2024.
Manager NEM Real Time Operations
[EventId:202411081430_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 08 November 2024 14:30
Issued by Australian Energy Market Operator Ltd at 1430 hrs on 8 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 November 2024.
Refer to market notice: 120143
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1430 hrs on 8 November 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202411081300_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 08 November 2024 13:00
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 8 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 8 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1300 hrs on 8 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/11/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 120135 has been updated at 1040 hrs to the following:
[1.] From 1800 hrs 08/11/2024 to 1930 hrs 08/11/2024.
The forecast capacity reserve requirement is 1124 MW.
The minimum capacity reserve available is 951 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 08/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120134 has been updated at 1040 hrs to the following:
[1.] From 1800 hrs 08/11/2024 to 1900 hrs 08/11/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1281 MW.
Manager NEM Real Time Operations