118198RECLASSIFY CONTINGENCY08/09/2024 07:14:05 PM

Cancellation of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown

Cancellation time: 08/09/2024 19:14

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 118185

Auto-generated on behalf of Manager NEM Real Time Operations
     
118197PRICES UNCHANGED08/09/2024 06:40:30 PM

[EventId:202409081815_confirmed] Prices for interval 08-Sep-2024 18:15 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1835 hrs on 8 September 2024

PRICES ARE NOW CONFIRMED for trading interval 08-Sep-2024 18:15.

In accordance with Market Notice 118186 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
118196PRICES UNCHANGED08/09/2024 06:39:24 PM

[EventId:202409081835_confirmed] Prices for interval 08-Sep-2024 18:35 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1835 hrs on 8 September 2024

PRICES ARE NOW CONFIRMED for trading interval 08-Sep-2024 18:35.

In accordance with Market Notice 118191 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
118195PRICES UNCHANGED08/09/2024 06:38:31 PM

[EventId:202409081830_confirmed] Prices for interval 08-Sep-2024 18:30 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1835 hrs on 8 September 2024

PRICES ARE NOW CONFIRMED for trading interval 08-Sep-2024 18:30.

In accordance with Market Notice 118190 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
118194PRICES UNCHANGED08/09/2024 06:37:33 PM

[EventId:202409081825_confirmed] Prices for interval 08-Sep-2024 18:25 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1835 hrs on 8 September 2024

PRICES ARE NOW CONFIRMED for trading interval 08-Sep-2024 18:25.

In accordance with Market Notice 118189 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
118193PRICES UNCHANGED08/09/2024 06:35:19 PM

[EventId:202409081820_confirmed] Prices for interval 08-Sep-2024 18:20 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1835 hrs on 8 September 2024

PRICES ARE NOW CONFIRMED for trading interval 08-Sep-2024 18:20.

In accordance with Market Notice 118187 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
118192PRICES UNCHANGED08/09/2024 06:36:31 PM

[EventId:202409081810_confirmed] Prices for interval 08-Sep-2024 18:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1835 hrs on 8 September 2024

PRICES ARE NOW CONFIRMED for trading interval 08-Sep-2024 18:10.

In accordance with Market Notice 118184 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
118185RECLASSIFY CONTINGENCY08/09/2024 06:09:07 PM

Reclassification of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown

Duration: 08/09/2024 18:09 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
118183MARKET INTERVENTION08/09/2024 04:02:49 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118174

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1400 hrs 09/09/2024.

The direction update is issued at 1600 hrs 08/09/2024.

Manager NEM Real Time Operations
     