117904GENERAL NOTICE27/08/2024 05:00:48 PM

Network Augmentation Commissioned - VIC Region - 27/08/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - VIC Region - 27/08/2024

Cressy - Golden Plains No. 1 220 kV Line has been commissioned.
Golden Plains Terminal Station has been commissioned.

Manager NEM Real Time Operations
     
117888SETTLEMENTS RESIDUE27/08/2024 03:30:23 PM

[EventId:202408271530_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 27 August 2024 15:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1530 hrs on 27 August 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 27 August 2024.

Refer to market notice: 117877

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.

The negative residue constraint NRM_QLD1_NSW1 ceased operating at 1530 hrs on 27 August 2024.

This is an AEMO autogenerated Market Notice.
     
117877SETTLEMENTS RESIDUE27/08/2024 02:37:01 PM

[EventId:202408271435_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 27 August 2024 14:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1435 hrs on 27 August 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 27 August 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.

The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1435 hrs on 27 August 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
117848SETTLEMENTS RESIDUE27/08/2024 12:30:27 PM

[EventId:202408271230_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 27 August 2024 12:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1230 hrs on 27 August 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 27 August 2024.

Refer to market notice: 117834

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.

The negative residue constraint NRM_QLD1_NSW1 ceased operating at 1230 hrs on 27 August 2024.

This is an AEMO autogenerated Market Notice.
     
117834SETTLEMENTS RESIDUE27/08/2024 11:36:54 AM

[EventId:202408271135_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 27 August 2024 11:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1135 hrs on 27 August 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 27 August 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.

The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1135 hrs on 27 August 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
117783POWER SYSTEM EVENTS25/08/2024 10:33:54 AM

Update - Non-credible contingency event - TAS region - 25/08/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - TAS region - 25/08/2024

Refer AEMO Electricity Market Notice 117782

At 1023 hrs the New Norfolk A 110kV Bus was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     
117782POWER SYSTEM EVENTS25/08/2024 09:24:53 AM

Non-credible contingency event - TAS region - 25/08/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 25/08/2024

At 0850 hrs the New Norfolk A 110kV Bus tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
117737GENERAL NOTICE21/08/2024 10:37:27 AM

Planned outage of Kerang - Wemen 220 kV line in the VIC region on 23/08/2024.

AEMO ELECTRICITY MARKET NOTICE

The Kerang - Wemen 220 kV line in the Victorian (VIC) region is planned to be out of service from 0600 hrs to 1800 hrs on 23/08/2024.

A credible contingency event during this planned outage may require:
- Load shedding in the Victorian outer grid; and/ or
- Market intervention, such as the issuing of directions.

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO Operations
     
117694GENERAL NOTICE16/08/2024 10:44:53 AM

Network Augmentation Commissioned - NSW Region - 16/08/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - NSW Region - 16/08/2024

Commissioned: Munmorah - Waratah S BESS 2Y 330 kV Line

Manager NEM Real Time Operations
     