118591MARKET INTERVENTION03/10/2024 04:33:16 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 118565

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 05/10/2024.

The direction update is issued at 1630 hrs 03/10/2024.

Manager NEM Real Time Operations
     
118590MARKET INTERVENTION03/10/2024 04:31:53 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 118560

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 05/10/2024.

The direction update is issued at 1630 hrs 03/10/2024.

Manager NEM Real Time Operations
     
118589RECLASSIFY CONTINGENCY03/10/2024 02:44:14 PM

Reclassification of a Non-Credible Contingency Event: Farrell - Reece No. 1 and No. 2 220kV lines in TAS due to bushfire.

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a Non-Credible Contingency Event: Farrell - Reece No. 1 and No. 2 220kV lines in TAS due to bushfire.

AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS

Lines: Farrell - Reece No. 1 and No. 2 220kV lines

Duration: 03/10/2024 1445 hrs until further notice

Constraint set(s) invoked: F-T-FARE_N-2

Manager NEM Real Time Operations
     
118587RECLASSIFY CONTINGENCY03/10/2024 12:11:42 PM

Cancellation of Reclassification of a Non-Credible Contingency Event: Glenrowan No1 66kV Bus- Vic region - 18/06/2024.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Reclassification of a Non-Credible Contingency Event: Glenrowan No1 66kV Bus- Vic region - 18/06/2024.

Refer AEMO Electricity Market Notice 117043

Based on advice from the asset owner, AEMO considers the trip of the following element is no longer reasonably possible. Accordingly its classification has reverted to a non-credible contingency event.


Region: Vic

Equipment: Glenrowan No1 66kV Bus

Cancellation time: 1215 hrs 03/10/2024

Constraint set(s) revoked: Nil


Manager NEM Real Time Operations
     
118586NON-CONFORMANCE03/10/2024 12:05:22 PM

NON-CONFORMANCE Region QLD1 Thursday, 3 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 3 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 03/10/2024 08:35 to 03/10/2024 12:05
Amount: -53 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
118571INTER-REGIONAL TRANSFER03/10/2024 09:29:33 AM

Inter-regional transfer limit variation - Bannaby -Sydney West 39 330 kV line - NSW region - 03/10/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Bannaby -Sydney West 39 330 kV line- NSW region - 03/10/2024

A planned outage of Bannaby -Sydney West 39 330 kV line in the NSW region was scheduled from 0700 hrs 16/09/2024 to 1600 hrs 11/10/2024.

The outage has been completed and Bannaby -Sydney West 39 330 kV line returned to service at 0920 hrs 03/10/2024

Constraint set revoked: N-BYSW_39_15M

Manager NEM Real Time Operations
     
118569RECLASSIFY CONTINGENCY02/10/2024 07:42:34 PM

Cancellation: Reclassification of a Non-Credible Contingency Event: Biloela -Biloela Tee 7110/2 132kV line and Biloela -Biloela Tee 7109/2 132kV line in QLD due to Other Threats.

AEMO ELECTRICITY MARKET NOTICE.
AEMO considers the occurrence of a non-credible contingency event due to other threats advised in AEMO Electricity Market Notice 118563 is no longer reasonably possible and accordingly its classification has reverted to non-credible.
Cancellation time: 1930 hrs 02/10/2024.

Manager NEM Real Time Operations
     
118568MARKET INTERVENTION02/10/2024 04:02:44 PM

Direction - SA region 02/10/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 02/10/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 02/10/2024.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations
     
118567MARKET INTERVENTION02/10/2024 03:37:19 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 118555

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2100 hrs 02/10/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 02/10/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     